Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...

how many 1st class bricks in 1cu feet?

Answer Posted / yaseen jan

volume of brick= .75'x.25'x.375'
volume=.070cu ft
now in 100 cft = 100/0.070
=> 1428.57 nomber of bricks
now 10% mortar /////
deduction of mortorr= 10x1428.85/100 = 142.85
nomber of bricks
so net number of bricks = 1428.57-142.85= 1285.72
now for contengencies = 5%
so => 5x1285.72/100= 64.28
now total nomber of bricks= 64.28+1285.72=1350.006 NOMBER OF
BRICKS
HENCED PROVED.





but The problem is that if we find the quantity of mortar in masonry wall we consider that 30cft mortar use in 100cft masonry wall. and if we find the numbers of bricks we deduct 10% mortar from 100cft. so in this situation we deduct 10% and if we find numbers of bricks its 30%. so some problem created here plz solve the problem.

Is This Answer Correct ?    11 Yes 0 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

reinforcement slab, beam and column formulas?

2689


which is the cheapest type of flooring (say for using for 6 months in a factory building & dismantling it)?

2087


how statics is different from dynamics

1674


Any strength is a stress but any stress is not strength

1822


sir tell me the formula for calculating the volume of 380mm dia double under reamed pile of 4.0 mts depth.

1988


VAT and CST ? Which benefits for buyer ? Why benefits?

1827


what is the effect of duration of earth quake on framed structures ?

2257


how to calculate cut length of re-bar in a circle . because we not place same length of re-bar in whole circle maximum in center and minimum at corner so how to calculate middle bars???

1917


What quantity of 1.0 m3 bricks required?

1144


why we can use dust in concrete insted of fly ash

2138


Reinforcement details at hinged joint

3158


I want to know the relevant IS codes of practice which deals with different testings of cement-sand mortar (nominal mix)that is being normally used for brick work or plaster work in the construction work.

2091


Analyze the rate for 1st class brick work in superstructure with 1:6 cement sand mortar. Consider 1000 cu.ft quantity and work out the rate per cu.ft

1886


Is it worthwhile to carry out tests on particle density of soil particles for geotechnical design?

1137


How to find permissible diagonal tensile stress in reinforced brick work

2536