Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...

How to calculate lap,bond and hook length for preparing bar
Bending schedule ?

Answer Posted / bharat hire

Lap length of bar depends on grade of concrete and design
bond. Owing to the Grade of concretes:

Grade of concrete) Tension Compression
M15 56.4d 45.15d
M20 47d 37.6d
M25 40.3d 32.25d
M30 37.06d 30.1d


For stirrups Hook length, it will be (-)2x10d
Bend, it will be (-3d) upto 12dia.
(-4d) above 12dia.

Is This Answer Correct ?    18 Yes 10 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

What is the Tor steel Consumption for residential building G+24 footing (thum rule) ?

1842


What is factor not to be taken in consideration in mix design?

3655


is it fair to recruit another prestressing agency once earlier agency has provided guide cone for post stressing the Concrete -I girders? It is observed that the bearing plate of another agency is not matching with the earlier one resulting in protruded strands after stressing from the face of girder. Kindly advice.

1946


what are the challenges of being a team leader and a supervisor?

3867


Explain the latest method to detect a crack in a building?

1160


Why the finite element method is lower bound solution?

2961


What is unit weight of normal concrete?

1284


Concrete cover for slab, column, beam and footing?

1086


What is difference between code and standard and specification?

2371


how to reduce size of column 450 x 750 to 230 x.... if it is cut in area of bathroom? means it appears in bathroon any shifting or any other option....building is g + 10 and the bathroom is at first floor...

2366


how many shuttering material required for 1000 sq.m built up area.

2358


With reference to construction of state highways, please let me know the total Bill Of Quantities as per the following details:- 1) Subgrade - 500 mm 2) Granular Sub-Base (GSB) - 200 mm 3) Wet Mix Macadam I (WMM I) - 150 mm 4) Wet Mix Macadam II (WMM II) - 100 mm 5) Dense Bituminous Macadam (DBM) - 60 mm 6) Bituminous Crust (BC) - 40 mm Road Length is 44 Kms. Road Width is 7 mtrs. Please provide the BOQ of each layer as per Compacted Factor & Loose Factor both. Also, if possible please provide me the approximate details of total material required (all categories viz. soil, gravel, stone aggregrate, sand, bitumen etc.) as per general mix design prevailing in India. Thanks & Regards -- Rokr

2445


How to calculate the crank rod in slab

2424


Caching, Multithreading and RAMBUS are 3 methods for resolving the Bottleneck problem. Please give an explanation for each one (how are they resolve the problem?)

2250


LET ME KNOW HOW IS CALCULATE RUBBLE WALL .3'00" IN BOTTOM 1' 6" IN TOP HEIGHT 8' 0" AVERAGE. length 200'00". please give correct answer.

2039