i want to change some data like price, data etc in created
purchase order. but system is not allowing the same. as a
support SAP MM functional consultant what you would do?
Answer Posted / sahasra
1. check whether po is open or closed.
2. check whether any release procedure is created for po, then release the po.
3. If GR is created against the po then it cannot be changed unless the GR is cancelled or changed
| Is This Answer Correct ? | 2 Yes | 0 No |
Post New Answer View All Answers
What is Material Document & Accounting Document in SAP MM.......
What about standard edition (initiate) users?
How will you consider sub contracting po components which are not sent by your company to vendor but they are added by the vendor (sub contractor)?
Explain the 'valuation area' concept in mm?
what are the types of special stock available?
What is the procedure to make the source list automatically appear in material master as default if maintained at plant level using ome5?
What are the features of sap erp?
What is a batch?
What are some of the movement types for stock transport order?
How much effort is it going to take to implement?
When a sales order contains normal(norm) and third party items(bans) how does the material reacts? Next order comes as make to order(0001), another is BOM. So every time we have to change the item category group in mm02 OR is there a process to expand the same material with norm, bans, 0001, erla?
What transaction code is used to convert planned orders (po) into requisitions in material requirement planning (mrp)?
Explain the 'storage location' in sap?
What do the we 103 do?
What mrp procedures are available in mm-cbp (consumption based planning)?