Answer Posted / rajesh.d.v.s.p.
normal design per square meter of slab we take 15kg of steel
hear thay given 100 sq.ft
1sq.ft = 0.0928sqm
100sq.ft=.0928*100=9.2 sq.m
total steel requried = 9.2*15=138 kgs
Is This Answer Correct ? | 8 Yes | 8 No |
Post New Answer View All Answers
what should be RCC material i.e iron rod(mm)x cement x stone x sand for laying of slab L 42'x B 22'x tk 0.375ft = 1nos & column of H 17'x15"x8" 2nos.
What is the FE 250 structural steel of 8mm tk plate testing sample intervals with IS code or international code?
can any one tell me in detail footing estimation .. i am new here in dubai so facing lots of problem...
Please design 12.5m long dubbly beam
What is the sugested procedure of water purification for public supply?
Dear Sir, I work in hydro project. I want to hire Scorpio/ Bolero on monthly basis. But how can i justified its amount (Hourly basic). Please solve my problem
What is the difference between the concrete mix design carried out by IS10262 and by ACI method ?
Please tell me vasthu room sizes. Thanks.
how to shuttering is used in slab
What is Base Shear ?
I Want To Know Quantity of Cement Conc. & Sand in Column of 9"x9"x10'
What is the coeffiencent Friction Angle between Steel and Ashphalt?
how to calculate spacing rod in column
What is difference between code and standard and specification?
punj loyed and sapurjl palanjl