Answer Posted / rajesh.d.v.s.p.
normal design per square meter of slab we take 15kg of steel
hear thay given 100 sq.ft
1sq.ft = 0.0928sqm
100sq.ft=.0928*100=9.2 sq.m
total steel requried = 9.2*15=138 kgs
| Is This Answer Correct ? | 8 Yes | 8 No |
Post New Answer View All Answers
how to calculate steel for slab or footings?
How is make concrete cube?
how to caliculate required amount of cement and sand required for 1cu.m.
Define a polyline?
I want some common questions which have been asked in interviews of NTPC Limited,Satluj Jal Vidyut Nigam Ltd.,and Bharat Heavy Electricals Ltd.
what are the ffactors you considered choosing the course?
what is kribs is supporting?
Could you please give me an answer to the mixing proportion of concrete M1 grade (sterngth of 1 MPa)?
How to increase a bearing capacity of soil?
What is meant by Crystal Concrete?
I want to know the relevant IS codes of practice which deals with different testings of cement-sand mortar (nominal mix)that is being normally used for brick work or plaster work in the construction work.
how much area can be platered by a mason for exterior
i have boiler of 35 tone and wanted dig out foundation is there any body to help me to carry out calculation for the foundation like
Hi I had missed my mark list (first year-apr2003)how i search in my old mark details in internet and which web site? pl inform me in full details..
Can rice husk ash be used instead of coal fly ash for manufacture of clc/ foam concrete