How to calculate the quantity of cement,sand,aggregate for the area L*B*T
are 15.24 m*21.36m*0.12m in the ratio 1:2:4
can any ine explain in detail by using formulas.
Thanks in advance
Answer Posted / karthik rajendren
Volume of Concrete = 15.24*21.36*.12 = 39 Cum
For 1:2:4 , Req.Cement Bag = 6.46 Bag/Cum , Sand = 0.44 Cum
, Agg =0.88 Cum.
For total Requirement,Cement = 41*6.46=264.86,Sand =
.44*41=18.04Cum,Agg=.88*41=36.08 Cum
(5% wastage's for Concrete is considered)
Is This Answer Correct ? | 9 Yes | 6 No |
Post New Answer View All Answers
what is box type waterproofing and how it is exsiccated and what is the method of doing box type waterproofing
How much cement and water required for cement selery????
how much quantity of cement,sand and water required for 1 sq feet flooring work .
what is mc arther pile?
Rate analysis of 150mm, 100mm, & 230mm thk BBM work
do we consider shrinkage factor for calculating cement consumption for CM mixes for different works?
how much quantity of 1.5" nails and 2.5" nails are required for conventional formwork shuttering?
Civil engineering related
to minimize budget cost of building , what can i do
Q 1) 1 Mason and 2 LABOUR / _________CUM brick work Q 2) 1 Mason and 1 LABOUR / _________SQ FT Plaster work Q 3) 1 Carpenter & 2 Labour/_________SQ FT shuttering work Q 4) 100 SQ FT roof slab concreting ____________mason and labour required
In jack arch floor, the rise is kept?
Describe the advantages and disadvantages of using plastic and timber fenders?
how i can calculate the actual nos & size of steel to make 1000sqft. x 3"thick slab
Which is the indian standard code of line out. ? How much tolerance fot 1 mt lenght? Its challenge....
3. What are the disadvantages of your present job, things you do not like about it?