what is relation between planned delivery and GR processing time .
Answer Posted / rajesh attade
Planned deliveruy means Number of calendar days needed to obtain the material and GR PRocessing time means Number of workdays required after receiving the material for inspection and placement into storage.
| Is This Answer Correct ? | 74 Yes | 2 No |
Post New Answer View All Answers
How can we create new transaction codes in sap?
Explain stock transfers?
Explain the types of gr blocked stocks in sap mm
What is a mrp area?
What is an indirectly created purchase requisition?
How you can link a document to a vendor master record?
Can you differentiate between a sto and standard purchase order at a glance? How?
Explain mrp type
What information is available in the 'accounting view' of a 'material master'?
What is a reservation?
What are the prerequisites of creating a purchasing info record?
What is an 'mrp area'?
when we doing migo storage location option not display
What is the differences between release procedure with classification and release procedure without classification? In which business scenario we use them?
Hi, I have 7+years experience In purchasing a new and doing sap-mm training, how is market for mm and how to find job as sap consultant, Pl help,