what is relation between planned delivery and GR processing time .

Answer Posted / rajesh attade

Planned deliveruy means Number of calendar days needed to obtain the material and GR PRocessing time means Number of workdays required after receiving the material for inspection and placement into storage.

Is This Answer Correct ?    74 Yes 2 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

Where the schedule margin key is customized?

763


What is purpose of gr based invoice verification in business? What is the business benefit of this check box?

809


Mention what are the major purchasing tables? List the transaction codes for them?

989


Explain the 'transaction keys' in mm?

710


What is *make to order?

627






Explain why a 'material master' is divided into views?

643


Why would an organization need to allow negative stocks?

748


what kind of L2 & L3 tickets are in SAP MM. Explain with example. Any enhancement done by you in SAP MM?? please help me in providing some real time examples

1153


If I implemented mdm very recently, should I upgrade?

654


Outline the functions supported by material master?

836


Explain how you can change the standard price in the master material?

634


What is the procedure to delete materials permanently from material master?

681


What is valuation grouping code related to obyc?

760


What are the data in the mm module that are maintained at the company code level?

687


What do the we 103 do?

684