how we can calaculate cutting lengh for stiruups 6mm dia .
column size 20 cm x 30 cm, cover 20mm
Answer Posted / chinnasamy
20CM X 30CM
200MM X 300MM
DEDECT COVER
200-20-20=160MM
300-20-20=260MM
HOOK LENGTH=10D
HOOK LENGTH=10X6
=60MM
DEDECT ELOCTION=2DX5CORNER
=2X6X5
=60MM
CUTTING LENGTH=(160+160+260+260)+60-60
=840MM
Is This Answer Correct ? | 3 Yes | 5 No |
Post New Answer View All Answers
The largest size of paper used in plotter to print the drawing made by Autocad .
What is thumb rule in quality and quantity estimation of a Residential building??
. Write a C program to perform following functions:- a. Declare one integer variable of all the storage classes. b. Print all the variables without assigning any values in tabular format. a. The tabular format must contain the variable name, type, storage class and printed value on the screen in RED color.
How to calculate woden area in sft and Cft
how calucate cement sand ratio for plstering
Coverage of 25mm.thick ratio of 1:4 cement mortar?
As per Kandal suggestions, we have implemented rolling starts on 140 (+/- 5) degrees and we kept 3 rollars to complete the rolling before falling 125 degrees and the Aggregate AIV is below 22. But When the DBM bed is being rolled 3rd high viabration, (Before 1 plain & low ,2 high Viabrations), the aggregate is getting sharp edge agg. projections are damaged. As the literature is said that, the VG-30 Grade having better control the temp. susceptibility than Penetration grade. if so we could not get this problem at site. But we are facing on site. let me know.
What is a projection line?
What is different between DI Pipe and CI pipe?
What is need for setting limits?
how pumping of concrete effects the quantity of material used in it?
What is the meaning of Brick- M 35 grade? Is it a common brick or it's a concrete brick?
how many type of admixtures for water stored structure?
will fix foundation bolts at site with out template is there any procedure?
Formula for calculating the volume of bulb in underreamed pile