Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...

how much time will take for G+22 building for completion?
activity wise like excavation,sub
structure,superstructure,finishing,handover?

Answer Posted / mohammed shahid

Well, there are many factors the completion duration depends
on and a duration for the project of G+22 cannot be derived
and said to be so-and-so months, as not everything stays
ideal and as planned.

1. For Excavation - Area of the building and the depth and
also the type of earth we're excavating. (Hard rock takes a
longer duration than the soil)

2. Sub-structure - As you've mentioned it is a G+22, i'm
assuming there is no basement but usually a G+22 has
2basements. Hence as per your question and details provided
we're omitting the basements but still the area of the
building plays a major role and also the structural (RCC)
vertical members and the types of foundations. If it is a
raft foundation, it takes lesser time with say A number of
manpower and if its isolated footings with a few combined
footings with the same A number of manpower then the
duration might triple.

3.Superstructure - Depends on the area, the vertical
members, the depth of the beams, structural projections,
number of lift shafts and staircases. One suggestion here is
the "SLAB CYCLE" can be derived and the same an be
multiplied by 22 for the entire structural (RCC) work of the
building.

4.Finishing - The same concept of "SLAB CYCLE" can be
derived and multiplied by 22 for the finishing duration of
the building.

5.Handover - This shall include attending to the snagging
list of activities and rectification works if any. the same
can be considered as approximately 60days.

Still if the Interviewer demands for a duration at the end
of the above explanation (presuming he will not), you can
give him an approximate figure of 24months maximum.

Is This Answer Correct ?    5 Yes 0 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

List out some of the common problems that architect have to tackle it?

1074


if we know load bearing capacity of the soil and building load falling in each footing, then how to choose the type of foundation??? and if it is shallow foundation then which type of shallow foundation should be choosen i.e either strip or isolated or raft or combined or cantilever footing???????

2300


what mean By core Billing

2309


What is the thickness of slab for 600 sq each) 2 slab construction. What should be the size of steel rod?

1825


What is reinforced concrete?

1107


How to arrive dry volume of concrete (1.52 to 1.57) ?

2341


what is the anchorage length of reinforcement.

1756


For Granite Flooring,For Cement Slurry purpose which one is effective of cost control whether OPC or PPC or White cement?

1954


What the advantages and disadvantage of using 90mm and 100mm bricks for a wall of a house? Thanks for any input.

1981


Forces in a Shear Wall are in plane or out of plane ?

1130


How to Calculate Materials Required for PCC 1:4:8 for 1Cum & Brickwork 1:4 for 1Cum & Plastering 1:4 (15mm Thick) for 100Sqm & RCC 1:4:8 & 2mt ( L1=1mt & L2=1mt ) length of 12mm Steel bended in 90degrees what is the formula to calculate Weight & Actual Length ?

11155


what is the coefficient for running feet to cft coversion both area and price

2393


Will water damage concrete?

1267


How much cement,sand,bricks and water needed for 1square metre brick work?

1814


Why steel rods are produced only in even dimensions?

2607