The ff slab casted its thickness
100mm.2nd floor slab will be casting its
300 mm.how we shall be given suppot to
that 300mm thk slab.ple way me
Answer Posted / unnu
Once the first floor slab is set , you can give support for the 2nd floor slab. Nothing is going to give away.FF slab will be already supported by columns
| Is This Answer Correct ? | 6 Yes | 1 No |
Post New Answer View All Answers
procedure for preliminary selection of size of column of 5 storey building
what happening if we casting HV shunt reactor foundation pad at 50cm height different time (One day difference)
how gradation of aggregates effect on slump of fresh concrete?
Define What is made from large rocks, which protects the base of cliffs?
What is the Roll of Water Bonding under VDF road?
How do you calculate reinforcement weight of steel?
What Is the Thumb rule to calculate depth and dia of pile required to carry specified load on differeent soil
If we are providing concrete joint in every 10m with water stopper in water tank wall then is it necessary to cut the steel at joint section?
How much quantity water should be placed in one cubic meter area?
What is meant by Crystal Concrete?
sir please send me campus placement questions in civil engineering
The definition of national highway
How to come 1.54 from dry to wet concrete?
1.How much batten required for 1 sqm Shuttering. 2.how much pipe & clamps required for staging of 100 sqm shuttering at 5.0 m height.
How reactor of SBR installed , is it be over ground, fully under ground or semi sunk ?