Answer Posted / neelam saroj
In column Lap length should be provided at mid height only
as per IS.
and it should be staggered prperly it means not more 50% of
of bar can be lapped at one section.
=}in general practice wht i do,
lap length should be above the slab at some distace or
below the beam at certain distance.
| Is This Answer Correct ? | 0 Yes | 0 No |
Post New Answer View All Answers
Hi.. Can i get hel in finding HPCL previous year question paper? plz help me in finding thiss..
What materials were used to build the golden gate bridge?
What is need for setting limits?
How to arrive dry volume of concrete (1.52 to 1.57) ?
Which is the direction for positive angle?
What is the compressive strength of fly ash bricks?
Is it worthwhile to carry out tests on particle density of soil particles for geotechnical design?
Define What is diversion tunnel in a dam?
Please send me the qunty. of mason/labour required in each day for different type of civil construction work?please send me ans. in my mail.my mail id is (parthamitra086@gmail.com) or here.
Iwant to calculate the production of 1 labour for concrete casting which includes shuttering,scaffolding,steel fixing,concreting, deshuttering and curing in 8hours.But i am not able to determine it approximately would you pls.??
indian standard split spoon sampler
How will you Engage Labours on Site?
how much percent are used 20mm,10mm?
What is c.g.i sheet which used for roof??
what should be RCC material i.e iron rod(mm)x cement x stone x sand for laying of slab L 42'x B 22'x tk 0.375ft = 1nos & column of H 17'x15"x8" 2nos.