The permissible wastage percentage are
1. Cement - 3%
2.Sand - 7%
3. Steel - 5%
4. Tile 10%
5. Aggregates - 3%
6. Bricks - 5%
7. Blocks - 5%
| Is This Answer Correct ? | 40 Yes | 21 No |
Post New Answer View All Answers
How do you maintain water pressure?
what is the water cement ratio for plastering
4. Differentiate between NC and OC soils. Draw curves for (i) Stress vs Strain (ii) Volume charge vs Strain (iii) Pore pressure vs Strain for these soils
Which is the latest version of solidsworks?
How to find coloumn vertical cut length floor to floor & lap + bend or anything plz clearfiy
What is the snap size in civil and how can we create it?
I was once rejected for US visa in early August. But now I'm going again for interview next week. What are the chances that I will faced the same VO????
How can i do RCC rate analysis?
1. HOW MUCH CEMENT AND SAND REQUIRED TO PLASTER 100 SQM WALL. 2. HOW MUCH CEMENT AND SAND REQUIRED FOR SCREED WORK OF AREA 30 SQM
Used Cement & Sand in 1 Square Meter or 1 Square Feet For Brick Work 0.115mm ? (1:4) (1:6)
1.what is the mix proportion for cement soil compressed earth blocks? 2.how to calculate the mix proportion for cement stablised earth soil blocks?
How much quantity of rod binding work by a rod binder per day
what is high type road and low type roads
Material calculation of cm 1:6 for 1sqm
What is quantity of cement and sand required for 2000sqft of tiling?