WHAT IS THE %WASTAGES OF CEMENT, BRICK,TILES, STEEL,IN 1
M3,10M2,1 TON RESPECTIVELY
Answer Posted / siba sankar sahu
The permissible wastage percentage are
1. Cement - 3%
2.Sand - 7%
3. Steel - 5%
4. Tile 10%
5. Aggregates - 3%
6. Bricks - 5%
7. Blocks - 5%
| Is This Answer Correct ? | 40 Yes | 21 No |
Post New Answer View All Answers
how gradation of aggregates effect on slump of fresh concrete?
Why steel rods are produced only in even dimensions?
Which stone is best for wall construction Laterite Stone or Cement Blocks
very simple or less time consuming formula for reinforcement calculation by moment
What are the methods of measurement? Describe it shortly
Requirement of cement, and steel 1:2:4 ratio concrete in 1128 Sqft area(Cement No of bags, steel in Kgs)
what are the five benefits of using standard terminology in the measurement process?
What is passive earth pressure ?
how statics is different from dynamics
20mm thick sand face plaster on walls consisting of 12 mm the backing coat of c.m.(1:3)and 8mm thick finished coat of c.m.(1:1)including scaffolding, watering, finishing etc complete please calculator with methyl et et r u
natucher of concrete &type of concrete?
please what are the required bars for a beams of 6mx6m and 450x300mm, one is continuous and the the second is discontinuous ..Its a commercial building (church)
How much time Required for PPR pipe network testing
what quantities of work done in terms of sq.mts/day/ of 8hrs for each varpenter (shuttering) and Steel fitter in terms of Tonnes. For slabs, Columns etc.?
how to decide the mortar ratio 1:4,1:6 in masonry? same in plaster 1:3 and 1:4? which code or any document reference taken to define proportion?