how much quantity a carpenter do shuttering per day
Answer Posted / nitin adate
Actually Shuttering output is depend upon type of
structure,height of structure, slab to slab height,shape of
structure, type of shuttering & most important availability
of skilled labour.But for planning purpose 2.5 to 3.00
sqmt /per day ( 1Skilled Carpenter + 2 helper ) is
reasonable value.
Is This Answer Correct ? | 103 Yes | 31 No |
Post New Answer View All Answers
for Precast foundation howmany days required we can shift the foundation with american Standards i need reference with section any body can help
What applicable rate of wct in bihar
How reactor of SBR installed , is it be over ground, fully under ground or semi sunk ?
Floor tile measurement? Wall to wall or skirting to skirting
what is the method used for marking of cantilevers in hirise buildings by using theodolite
what is the Purpose of Adding 20% of wet mortar & 1/3rd to Dry Mortar for PCC & Plastering & Rcc .is there any standard method for adding this .?
how the calculation occurs if i want to mix 1cum of M50 concrete. please calculate every ingredients with detail calculation.
What is specific gravity???
What are new methods /technologies of pothole patching?
Define graphics window?
what is the use of steel rods of 16mm or 20mm used for 4.45mts for closing gutter.one mate consumes how many kgs with a gap of 6inches.
sir, whitch is the best book (writer name) for prepration of gate....
how to find ssm in foundation?
400 ku d/c clearess ketan hota hai?
please send latest placement papers of hpcl officers trainee test. i will be very thankful to you.