Used Cement Mortar, Cement & Sand in 1 Square Meter or 1
Square Feet For 10-18mm Thick Plaster ? (1:6) (1:4)(1:3)
Answer Posted / uttam sasavade
If 1:4 Plaster Qty for 100 M2
= Wet Volume of Material 100 m2 x 0.018= 1.80 m3
= Dry Volume consider 25 % extra= 1.80 m3 x 1.25 = 2.25 m3
required.
1/5 =0.200 * 1.25= 0.25 / 0.0347bag= 7.204 bag req. for 1 m3
Cement required for 2.25 m3 x 7.204 bag= 16.209 bag.
Qty. required for 1 m2= 16.206 /100 = 0.16 bag
Sand 4/5= 0.8 * 1.25= 1 m3 x 2.25 m3 =2.25 m3 /100
sand Required for 1 m2 plaster 0.0225 M3
| Is This Answer Correct ? | 4 Yes | 2 No |
Post New Answer View All Answers
Define block?
What is the difference between Fe 500, Fe 500 D and Fe 515.
1. 1. The mass of a chunk of moist soil is 34 Kg and its volume is 0.012 cu. Meter. After drying in an oven, the mass reduces to 14.25 Kg. Determine the water content, the density of moist soil, the dry density, void ratio, porosity and degree of saturation. Take G = 3.25
How to calculate the weight of sand am 20mm course aggregate in 1 c.m M25 concrete Which use 400 kg of cement ?
satart to end steps by step process of building construction...? i want to planning theme accuretly
how much quantity of 1.5" nails and 2.5" nails are required for conventional formwork shuttering?
How much of the strength of concrete comes from post- production curing?
If a slab concrete is placed with M-20 grade concrete, actually it has to be placed with M-30. what are the rectifications / measures to be taken after concreting is done.
show answer/ calculate-1-2-4 ratio-concrete -cement-sand- metal-water - please brief calculation
Minimum concrete cover in slabs, columns, beams, foundation and other st?
How to Rectify deep crack formed on Brick Wall? Explain the method of rectify the defect?
What is pre-stressed concrete?
Design a shear wall of length 4.20 m and thickness of 250mm subjected to the following forces.Assume Fck = 25Mpa and Fy = 415Mpa and the wall is a high wall with central part 3440mm x 250mm and two 380mm x 760mm strong bands at each end with following loading. S.No. Loading Axial force Moment Shear 1 DL+LL 1950 600 20 2 Seismic load 250 4800 700
Howmuch bend to be provide for 200/600 BEEM
do we consider shrinkage factor for calculating cement consumption for CM mixes for different works?