what are the Cement Coefficient for Block Work & plastering
Work?
Answer Posted / ballal
Siporex Block Work has 0.18/sqm of cement consumption whereas
Plastering Work
a)External Plaster 1st coat 0.13/sqm
b)2nd coat comprising of 0.08/sqm,
c)Internal Plaster has 0.13/sqm.
| Is This Answer Correct ? | 4 Yes | 0 No |
Post New Answer View All Answers
How to calculate quantity of cement , sand and granite from concrete mix ratio and volume of work
what is thumb rule for calculating the size of ISMB required for a particular length of span
How will you Engage Labours on Site?
how much cement is consumed by a stone masonry wall 17.7m long,0.55m wide and 1m high
hoe much fine & sourse agregate required for concrete mix of 1: 1.5:3 by volume in Cu.Ft
What is OSHA compliance?
how to absorb to site basic corrections? which are the important correction?
What is absolute pressure? How absolute pressure is calculated?
density of crush sand & crush stone or grit powder
what is castigliano theaorem
How you can turn off the display for dimension in CAD?
How much percentage of brick bats allowed in CD-75 bricks
what is zone a n zone b?why the spacing of ring in zone a less.n zone b high?
Can anyone suggest how to determine scheduling of reinforcement of floor beams from Staad model,other than clicking each beam respectively 7 noting down the values ?
Please let me know about answer for my Question as "What is the maximum wastage allowable of HYSD Steel in any Bridge project as per Code and Code reference also ?