what is right time of slab DE shattering and beam boo tam.
Answer Posted / sagar tiwari
span length over 6m than 28 days
span length below 6m than 14 days
span length over 4.5m than 14 days
span length below 4.5m than 7 days
| Is This Answer Correct ? | 0 Yes | 0 No |
Post New Answer View All Answers
how to calculate load bearing column
A Cat excavator loader of 3Lm*3 heaped capacity bucket is to be used to load blasted rock directly into a crusher of capacity (consumption) of 100L
How many pyramid in egypt?
How to calculate laplength for 3 floors
What in your opinion makes you the most suitably qualified candidate for this post of civil engineering technician?
what is the hanekom repairing material after concreting work
if a pipe those configuration (ASTM c 76 class b 450mm dia 2500mm length) fixing for water course those lining of water is 7000 running meter. my question is that if 8 joints of pipe ls leakage and we have not permission to stop the water so which treatment we apply on joint in that in condition.
Which architectural movement is also known as jazz moderna?
What is the FE 250 structural steel of 8mm tk plate testing sample intervals with IS code or international code?
How to find out kg per Sft ?
What are the methods in tiles flooring ? What are the methods in brick work? What are the methods in plastering ? What are the methods in wall tiling?
Which is the direction of negative angle?
manhole chamber having height of 2300 mm and thickness of brickwork is 230 mm and dia of opening covering is 560 mm and bottom length vertical is 1500 mm (1:4) brick masonry and plaster 12 mm on both sides..how to estimate the no bricks used with mortar cement bags and sand for total chamber including plaster.
Slab quantity
How much quantity water should be placed in one cubic meter area?