Bitumen grades are 30-40,60-70, 80-100. what is mean by 30-
40
Answer Posted / ujjawal u. d.
the penetration caused by standard Condition i.e.
Standard Weight= 100 gm
Standard temp. = 25 Degree C.
Standard penetration time = 5 Seconds
Unis = 10th of mm to show the results and avoiding Errors
e.g. if the value is 30/40, the 30/40 is the bitumen
penetration value (tested in standard condition) lies
between 3 to 4 mm.
| Is This Answer Correct ? | 109 Yes | 7 No |
Post New Answer View All Answers
I used Etabs software to analyse a high-rise building. And I want to use templated UBC-codes inside to calculate the Seismic load. My question is: whether or not I have to control the seismic load by base shear load which is manual calculation? (just for more clarification: I can control this by input the scale factor into Eartquake definition in Etabs) I would highly appreciate your answer.
Hi all, please guide me about the volume. And percentage. Of steel fibre to be used. My project. Is Sifcon.
What is the best type of wood glue?
what are the duties of Site Engineer in work site?
what is the difference between prime coat and tack coat in road construction
What applicable rate of wct in bihar
How Can I know the wastages(%) of each work added in estimating the quantity of construction materials?(Eg. Ceiling Work, Brick Work,etc....)
When was the first motorway built in england?
If we are providing concrete joint in every 10m with water stopper in water tank wall then is it necessary to cut the steel at joint section?
Which percentage of carpet area use in plot area of office building.
How to Calculate Materials Required for PCC 1:4:8 for 1Cum & Brickwork 1:4 for 1Cum & Plastering 1:4 (15mm Thick) for 100Sqm & RCC 1:4:8 & 2mt ( L1=1mt & L2=1mt ) length of 12mm Steel bended in 90degrees what is the formula to calculate Weight & Actual Length ?
Why we provide hair pin for shed
What is the difference between Hinged and pinned in Column ends
What is a kip?
What is made from large rocks, which protects the base of cliffs?