how can we calculate cutting length of a column ring
(300 x 600)
Answer Posted / md nahid akhtar
assume c.cover of column 30mm.
so, 2(L+B)+24D
where, D= dia of steel bar.
sol,assume dia of steel bar= 8mm
=2(540+240)+24*8
=1752mm.(cutting length for col ring)
| Is This Answer Correct ? | 10 Yes | 22 No |
Post New Answer View All Answers
how to caluclate sienerge qty in construction in ap
Minimum and maximum size of the building components
Kindly post me previous year interview questions with answer for post of DY. Manager (civil engg.) for GAIL, NTPC, IOC, OIL and ONGC etc.
How you can use different dimension tools in cad? What are the different dimensions available?
I am in India. Employer A got approval for my H1. But they have no job for me now. Company B is going to file H1 for me. They do not know about company A. Is there any way that I get approved H1 of company A transferred to Company B?
How much material will consume for following specification water tank (9*7.5*6 feet)?
how calucate cement sand ratio for plstering
In tower foundation, on the time of 3 mtr pit RCC casting if water and mud is their surface of PCC then what will be do?
In foundation design, while we do the base pressure check, we normally check if the attained pressure value is less than the GROSS BEARING CAPACITY of the soil which is the sum of net bearing capacity of soil and the overburden pressure. Actually, the overburden pressure acts against the net bearing capacity of the soil and I feel that we are actually increasing the bearing capacity value and doing the check. I feel that this is NOT right. Please clarify on this.
why is M30 grade Concrete use for Foothing & Column M50
Please tell me Detail cost of providing& laying nominal mix design 1:2.5:5,40mm nominal size.curing complete e/c cost of form work in foundation and plinth i/c carriage.
Maximum cement content in 1cum for RCC and PSC? (please give IS,IRC referance?
What do you mean by bond? What are the different types of bonds?
Formula for calculation volume of essentric footing
How to do base isolation for RC framed structure using ETABS software?