Trapezoidal footing length = 2m , B=1.7m D=0.5m and d-
0.15m. Can anybody help and calculate quantity of concrete
by explaining all formulas involved.
Answer Posted / anand shinde
h=(D-d)
(D-d)/3x(a1+a2x(under root a1xa2)
| Is This Answer Correct ? | 0 Yes | 1 No |
Post New Answer View All Answers
What is the meaning of Brick- M 35 grade? Is it a common brick or it's a concrete brick?
what radial pressure, the NP2 class rcc pipe can sustain?
What is Critical path in Ms-Project ?
how to calculate Rate of analysis for 100 m3 Any ratio of concrete ? including labour
Rate analysis of 150mm, 100mm, & 230mm thk BBM work
Design a reinforced concrete combined footing (rectangular) for two columns located 3.60 metres apart. The overall sizes of the columns are 40cm x 40cm and 69cm x 60cm and the loads on them are 1000 kn and 1500 kn respectively. The space available for the width of the footing is restricted to 180cm. The S.B.C. of the soil is 280 kn/mm2 use M15 concrete.
what is the clear cover for shearwall?
how many digree of freedom in four bar chain
1.what type of the rock is most suitable for wet mix macadam in construction of road? 2.what is the highest maximum dry density and optimum moisture content can be acheive by using most suitable crush rock?
silt%= silt volume/ silt+sand volume is this right?
please send me bhel questions on rupesh.017@rediffmail.com
what is tension column?
what is the design procedure for building
Define mirror?
how water proof chemicals act in concrete to avoid leek?