200sq.ft of slab and thickness is 6" in that how much cement
are required(bags), sand & aggregates are in cu.m, choose
grade of concrete is m20.
Answer Posted / shivang
cement bags= 23 bags=((1/5.5)*1.57))/0.035
Sand = 1.21 m3= ((1.5/5.5)/1.57))*2.83
Aggregates = 2.42 m3= ((3/5.5)/1.57))*2.83
| Is This Answer Correct ? | 6 Yes | 0 No |
Post New Answer View All Answers
Define What happens to Load at yielding ?
what is the water cement ratio of 1:6 and 1:4 cement sand mortar. reply soon
Questions related to civil.engg in company
how to determine the correctness of proportion used in cement mortor and various IS codes to determine the same?
Explain the different types of building contracts?
How about the temperature of grade 35A concrete? Does it depend on the ambient temperature?
You have 3 snd sample of different FM=0.21,FM=0.95,FM=2.90 which one is suitable for a)plastering on R.C.C b)plastering on masonary wall c)concreting column d)concreting of bored pile.also justify your answer.
How you can turn off the display for dimension in CAD?
List out some of the software used in the construction sector to estimate cost and monitoring expenses?
what is meaning of inverted beam.is it way to provide double mat in slab one at bottom and another at topif we go for provision of inverted beam. shall we construct structure with out plinth beam for us we have to construct small bus shelter
Define What is aggregate?
How to fix the reinforcement in footing shorter bar at bottom and longer fix at top.
reinforcement slab, beam and column formulas?
Did any of the egyptian pyramids ever fall down?
Why Should Curing Not Be Done By Ponding And Polythene Sheets?