Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...

200sq.ft of slab and thickness is 6" in that how much cement
are required(bags), sand & aggregates are in cu.m, choose
grade of concrete is m20.

Answer Posted / shivang

cement bags= 23 bags=((1/5.5)*1.57))/0.035
Sand = 1.21 m3= ((1.5/5.5)/1.57))*2.83
Aggregates = 2.42 m3= ((3/5.5)/1.57))*2.83

Is This Answer Correct ?    6 Yes 0 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

Why should pumping be not used in case of concreting works?

1476


What is the difference between routing maintenance and major maintenance in school facilities?

1167


What is binding spacing of the rebars at lapping zones.

1357


How do You Maintain a structure after getting cube test of low strength.

2370


What is .Dwg?

1347


What should be the maximum allowable time for placing ready mix concrete? The specification requires concrete placement within 90 minutes of batching at the plant. What is the significance of this 90 minutes & should this be used as a rejection criterion? What effects does the concrete has after that time period?

2913


What is difference between code and standard and specification?

2435


How to improve the strength of fly ash bricks to avoid corner damge? How to get the color lighter similar to normal concrete blocks/

1915


 Which Types Of Bricks ? 

3116


What are your goals?

2993


What is labor and material payment bond?

1200


how many sqft or cft of work done by a mason per day in all works such as brick,block,concrete,shuttering carpenter,reinforcement fabricator,painter,door window carpenter.....everything thank you

2117


Questions related to civil.engg in company

2073


how to calculate quantity of cement,sand & aggregate for u.c.r / r.r masonry in cm 1:6

6278


on what basis the partial factor of safety are decided? form the load combinations

2287