how to calculate rate analysis of M25 grade concrete
Answer Posted / karthik rajendren
Cement - 7.2 Bags*280 = 2016
Sand - 0.6 Cum*400 = 240
Aggregate 20mm - 0.9Cum*890=801
Plasticizer - 2.1 Kgs*50=105
P+M - 450/Cum
Total = 3612
Note
*The rates may vary depends on location
*The cement bags 7.2 is as per design mix,it may vary if we
choose hand mix
| Is This Answer Correct ? | 5 Yes | 12 No |
Post New Answer View All Answers
What Reinforcements Are Used In The Process Of Prestressing?
explain five benefits of using standard terminology in the measurement process?
What is the difference between absorption & adsorption and sorption?
How do you compute the volume of airflow?
Why are pull-out tests performed for soil nails?
How to arrive d*d/162 , for finding the kg per meter , wt of steel
what is anchorage length,lap length and (dont remember the last one)
Explain the advantages and disadvantages of using plastic and timber fenders?
Does brick grows bigger every year?
I used Etabs software to analyse a high-rise building. And I want to use templated UBC-codes inside to calculate the Seismic load. My question is: whether or not I have to control the seismic load by base shear load which is manual calculation? (just for more clarification: I can control this by input the scale factor into Eartquake definition in Etabs) I would highly appreciate your answer.
what is box type waterproofing and how it is exsiccated and what is the method of doing box type waterproofing
What are some facts about concrete?
how to identify np3 pipe and np4 pipe
from one meter cube of stone masonry structure how much cubic meter of cement mortar we use as our estimation 25-30% is that correct for estimation of quantity of sand and cement(2:1) proportion of mortar
how to compute slab reinforcements on step by step procedures??