ground floor columns and beams are reinforced by 4 Num's 16MM @ Corners AND 2 Num's 10MM @ centre.... And the nxt top floor columns and beams were lapped by 8 num's 12MM dia bars.....
IS THIS CORRECT ????
Answer Posted / rc
incorct method....of steel binding
Is This Answer Correct ? | 1 Yes | 1 No |
Post New Answer View All Answers
hi guys what happens if you are absent for a supplymentry exam?
how to stop beam concrete between column
How to Rectify deep crack formed on Brick Wall? Explain the method of rectify the defect?
What are some structures that may be subjected to fatigue?
pile load testing procedure
Journal entry Gross salary 10000 Tax 1000 Employee contribution 2000 Employer contribution 2000
what are the ffactors you considered choosing the course?
What is Joule Brayton Cycle?
States some of the commonly used commands in cad software’s?
how to take the quantity of block work and plastering 1block price:3saudi riyal cement:1bag:15 saudi riyal sand:3bag:20 saudi riyal 1mason:9hour per hour 40 saudi riyal 1labour:9hour per hour 40 saudi riyal can anybdy calculate
what is the steel difference between np-2 and np-3 pipes and weight also
percentage of metal,clay or soil & water in water bond macadam roads to know the quantities for each in total volume of 11500 cubic meters
cause of cylinder test failure
What should be the maximum allowable time for placing ready mix concrete? The specification requires concrete placement within 90 minutes of batching at the plant. What is the significance of this 90 minutes & should this be used as a rejection criterion? What effects does the concrete has after that time period?
What is factor not to be taken in consideration in mix design?