Answer Posted / sjtbehera
Approximate method to determine the qty of material of mortarfor 10cum brickwork- divide by 3 by the4 sum of numericalof the proportion of material which gives the qty. Of cement in cum. So 1:4=
3/1+4= .6 cum i.e 18 bags in 10 cum
Sand= .6 x 4 = 2.4 cum
It is ony applicable in 10 cum brickwork
You can try this method
| Is This Answer Correct ? | 0 Yes | 1 No |
Post New Answer View All Answers
how much deduction will be in 32 mm dia HYSD steel bar for 45 and 90 degree bend
What difference comes in constructing of house and a housing complex like society
Consumption of Binding wire for fixing of cover block in vertical surface
i have four storeyed rcc building.basement of the building is around 34 years old.it does not have pillar support.it is having lintel steel support at every 7 feet of construction. how long this building will lost long . can any body help me in this regard
what"s the sort of beams?
what is the anchorage length of reinforcement.
How can explode a block?
Define aligned dimension?
WHERE CAN I GET THE PREVIOUS QUESTION PAPERS OF APGENCO FOR THE THE POST OF Tr.ASSISTANT ENGINEER(CIVIL)
how to calclate the SHUTTERING TAKEN CONCRETE LOAD? WHAT IS THE LOAD BEARING CAPACITY IN STEEL SHUTTERING PLATE? WHAT IS THE CONCRETE LOAD IN (MASS) IN THE SHUTTERING PLATE. PLATE SIZE IS 120CM* 90CM CONCRETE WALL LENGTH IS 10M ,WIDE IS 60CM, HEIGHT IS 1.2M PLS TO SENT THE CALCULATION.
What you understand by building codes?
What is GSB gradation
How foundation is designed, Column design and beam design
what is conventional shuttering rate per square feet of built up area? what is Mivan shuttering rate per square feet of built up area? what is coupler shuttering rate per square feet of built up area?
why we are useing plastic under the lean concrete?and whts the advantage?