Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...

1) One mason per day how many cu.m work will do as per list
given a) Brick work,hollow brick work and cc block work and
plastering how many m2 per day 2) one carpenter per day how
many m2 will do as well as scaffolding how many m3

Answer Posted / gowrishankar

Plastering per day 8 hours one mason and helper will cover 10 m2

Is This Answer Correct ?    321 Yes 61 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

Define What is passive earth pressure ?

1223


What is demising walls?

1158


Slab quantity 

2029


Whats the meanig of ,'K' VALUE in the case of soil.....

1987


What are the RISKS during the project construction?

2283


how calucate cement sand ratio for plstering

1976


Prepare a Schedule for a Highrised building from starting stage to Handover?

1977


what could be the production cost of 1 cum of concrete by CP30 plant

1699


Currently my house construction is going on but we just realized that the portico earth beam couldn't connect with the original earth because the beam rod not extended so Please advice

2640


how to convert sand in Cft to Kgs

1930


Define What are the materials used in building a gravity dam?

1248


The internal dimensions of a wire house 15m*5.6m and the maximum height of piles is 2.70m. What is the maximum number of bags to be stored in two piles ?

2223


What is bmc stands for in bmc software?

1167


I have a slab of 20cm thickness of 20m by 4m in wich we are installing 15 tons electric panels , and we have put 4 H-shaped columns under the slab but we have done many cores in the slab which seems very normal , can you help me by telling me how to calculate the bearing capacity of the slab or give me an idea if i should increase more columns Note: load distribution area 12*1.5 m2

2310


which is the cheapest type of flooring (say for using for 6 months in a factory building & dismantling it)?

2078