for 100 sqm cement concret (1:2:4) 4cm thick floor,the
quantity of cement required is
Answer Posted / ketan shinde
100×.04=4cu.m of wet concret
To produced 1cu.m of concrte 1.54cu.m of dry concrte required
1.54×4=6.16cu.m
6.16/1+2+4=.88 cu.m of cement reqd.
.88×1440 (densityof cement)=1267.2 kg
Or
1267.2/50kg =25.34=26 bag of cement
| Is This Answer Correct ? | 31 Yes | 9 No |
Post New Answer View All Answers
What is the density of most of construction materials?
Which is the direction for positive angle?
I have to conduct load test on greting cover, pressure gauge is in kg cm2, how to caluculate load on this greting cover.
how many minimum admixtures are used in water froofing structures
what is the anchorage length of reinforcement.
for 32 dia (EQR HYSD steel) bar how much deduction for 45 and 90 degree band
What are the applications of modulus of elasticity?
What are the basic use of runners and standards of pipelines?
I want to know how much the lapping length for the pilecap reinforcement.. we r using single pile cap which is 24mby54m and 2.5m depth.. total 91piles are supporting the pile cap.. how to do a steel reinforcement??
pls give me ans to ACT formula cube testing porpuse
what is flashing?
What is the nature of duties & responsibilites senior civil engineer ?what is self confident & satisfaction should be a senior civil engineer?
strength vs shape factor
What is progress payment?
i have boiler of 35 tone and wanted dig out foundation is there any body to help me to carry out calculation for the foundation like