for 100 sqm cement concret (1:2:4) 4cm thick floor,the
quantity of cement required is
Answer Posted / ketan shinde
100×.04=4cu.m of wet concret
To produced 1cu.m of concrte 1.54cu.m of dry concrte required
1.54×4=6.16cu.m
6.16/1+2+4=.88 cu.m of cement reqd.
.88×1440 (densityof cement)=1267.2 kg
Or
1267.2/50kg =25.34=26 bag of cement
Is This Answer Correct ? | 31 Yes | 9 No |
Post New Answer View All Answers
The portion of a brick cut across the width is called?
What is the compressive strength of fly ash bricks?
how many shuttering material required for 1000 sq.m built up area.
on what basis the partial factor of safety are decided? form the load combinations
In cement concrete how to check a quality of material also proportion of material at site ?
how to reduce size of column 450 x 750 to 230 x.... if it is cut in area of bathroom? means it appears in bathroon any shifting or any other option....building is g + 10 and the bathroom is at first floor...
in a corner footing of a building, column lies in one corner. in this condition i want to know if the reactive pressure of soil will be uniformly distributed throughout the footing or will be uniformly varying as in the case of eccentrical loading.
Explain major differences between routing maintenance and major maintenance.
How much quantity of cement and sand required for the inlining of 610mm dia MS pipe 8.7mm thk.Inlining thickness is 10mm and CM ratio is 1:1.5.
If u want ur Ans.Of any Question so mail me skatiyar011@yahoo.in
Write short note on construction programme for pile foundation.
how much shouid be the rate for ready mix concrete per cubic meter
I need model question papers for writing the Dubai municipality exam,for G+1
all technical question
What is geopolymer based concrete?