Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...

how we can calaculate cutting lengh for stiruups 6mm dia .
column size 20 cm x 30 cm, cover 20mm

Answer Posted / usman ali

128.88cm is the correct answer
in total length must add 2 numbers of hucks 15.24cm+15.24cm

so the corrrect answer is 128.88cm

Is This Answer Correct ?    1 Yes 4 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

Can inverted beams used in pipes during construction?

1305


Which ratio use for cement selery???

1881


How many pyramid in egypt?

1011


how to calculate 1:5:8 ratio concrete cement, sand, metal and water please give me brief calculation

1721


In reclamation works what are the importance of geotextiles and sand?

1118


What is the ratio of grades m5, m7.5, m10, m15, m20, m25, m30, m35, m40?

1139


what is constat for brickwork

2129


In case if concrete box girder bridges how is the number of cells determined?

1151


How many square meter can mason layout chb per hour

2221


Pls help me to arrive the rates for centering shuttering for highbay using H-frames?

2313


How musch steel i.e. angles, channels,and square pipes are required per square feet for a steel roof of residential two storied building?

1752


How are freeway bridges built?

1219


Analyze the rate for 1st class brick work in superstructure with 1:6 cement sand mortar. Consider 1000 cu.ft quantity and work out the rate per cu.ft

1846


how to take the quantity of block work and plastering  1block price:3saudi riyal cement:1bag:15 saudi riyal sand:3bag:20 saudi riyal 1mason:9hour per hour 40 saudi riyal 1labour:9hour per hour 40 saudi riyal can anybdy calculate

2432


how to calculate the scour depth

2859