DG B-check,C-Check,D-check is depending upon the running
hrs.If the running hrs is not reached as mentioned.How to
conduct the DG checks.
Answer Posted / rajakumar k j
this check is preventive maintainance of DG sets(1000-1500KVA).
1) A-check is done on daily basis here we check:
a) oil level
b) coolant level
c) gauge valve level
d) check for any leakage.
e) cleanliness of DG set.
2) B-check(done after 300hrs of cycle or 6 months whichever is earlier. )
a) check lube oil filter
b) fuel filter
c) air filter
d) bypass filter
3) C-check(done after 1500hrs of cycle or 3yrs whichever is earlier.)
a) all steps of b-check.
b) check/change of air filter (if needed).
c) check/change of other filters mentioned in b-check.
d) change of gaskit of chambers.
4) D-check
a) done in 6000 hrs of cycle.
| Is This Answer Correct ? | 2 Yes | 0 No |
Post New Answer View All Answers
if we give 60 hz single phase supply to the transformer used in europe , than what will happen
could an induction motor be used for regenerative braking in electric-train control? in this type of application would some scheme have to be devised to obtain low synchronous speeds while braking? would induction-motor drive, therefore, be suitable for passenger service?
Initially, when the input is not equal to the output — what type of response is this?
defination of controlled shunt reactor
The Howland current source produces a A Unidirectional floating load current B Bidirectional single-ended load current C Unidirectional single-ended load current D Bidirectional floating load current
Define average demand?
What is Tachometer used to measure?
whether fibre optic cable in high voltage earth conductor is used for protection circuits
Define peak time.
What are the main significances of root locus?
What happens when ac supply is given as excitation voltage instead of dc supply
I want formula to calculate current loss with distance in km.I searched many sites but didn't right answer.Plz reply me
Installation resistance for whole installation of 16 kva & 25 KVA DTRA a) Between each conductor b) between conductor to earth c) installation resistance for each apparatus, each conductor to earth d) earth resistance for the system of earthing
How to synchoronize the generator (with gcb,GT) to grid????? ????? from Grid iam getting power (rated 400kv/20kv) through GT and its goes to UAT.,,ST.,, now my generator(rated 20kv ) ready.,, now iam closing my GCB.,, in GT iam suddenly giving 20kv on that Gt.,, what will happend
Explain how to determine capacitor tolerance codes?