How to calculate the cement, sand quantity for plastering?
(10'x10')10mm thick ratio 1:5. wht"s the formula?
Answer Posted / rakesh sinha
Total Plaster Qty.=.09cum
Wastage 20%=.02cum
Total Qty.= .11
Cement 1cum=1440
Sand 1cum=1600
Ratio of cement and sand=1:5
so,
cement ratio=.0186
sand ratio=.0929
cement required
1440*.0186=26.76kg
sand required
1600*.0929=148.65kg
| Is This Answer Correct ? | 1 Yes | 2 No |
Post New Answer View All Answers
What is a bearing capacity of soil?
how to find hardness of water?why it should be determined?
how many re use can use shutting material. timber ? ply? steel? plastic? fibre? aluminium? Doka?
insted of bentonite we can use any alternate material in piling ?
manhole chamber having height of 2300 mm and thickness of brickwork is 230 mm and dia of opening covering is 560 mm and bottom length vertical is 1500 mm (1:4) brick masonry and plaster 12 mm on both sides..how to estimate the no bricks used with mortar cement bags and sand for total chamber including plaster.
In the present situation of ban on mining sand from rivers,can we go for formation of earth dam filters viz;Horizantal sand blanket,inclined chimney and filters under rivetment with crushed rock sand of 6mm down size.If so what are the specifications and is there any codal provision for its authentication?
If 40 backlogs are cleared m finally with 65 percent marks . Am I eligible to get visa to US
percentage of metal,clay or soil & water in water bond macadam roads to know the quantities for each in total volume of 11500 cubic meters
What is the tallest man made structure in the world?
what is difference between NP2 NP3 NP4 CONCRETE HUME PIPES USED AT SITE
Why reinforcement done in shorter span in two way slabs
what is conventional shuttering rate per square feet of built up area? what is Mivan shuttering rate per square feet of built up area? what is coupler shuttering rate per square feet of built up area?
how to conversation of all construction material in to brass
the water is flowing through a velocity of 1.5m/s in a pipe of length 2500m and dia 500mm. at the end of pipe a valve is provided. find rise in pressure 1. if the valve is closed in 5 seconds. 2. if the valve is closed instantaneously. take value of c = 1460m/s, pipe to be rigid and bulk modulus of water - 19.692x10' n/sqcm
Formula for calculating the volume of bulb in underreamed pile