Answer Posted / syed shahid
The steam pressure in the last stage of the steam turbine
is very low after performing the work. To make the steam
flow to the condenser to convert into condensate
(liquid/water)it is necessary that the pressure be much
lower in the condenser to make the steam flow to the
condenser.Therefore, vacuum is maintained in the condenser
using either vacuum pump or steam ejector.
| Is This Answer Correct ? | 100 Yes | 11 No |
Post New Answer View All Answers
how is the cable tray designed & how its total length is calculated for an Industrial plant Say for Ex. (500KW Motor Load)
how to put cable sizing and cable glands size for respective cable & Cable Lug size in a DB sectors???
do any one help me to get "C" license,, i have doubts ,,, if mediators ter pls call me,, my no is 8056640042
Define active and passive network?
Load break swicth maintenance procedure.
explain remenance . differentiate high remenance type ct & low remenance type ct
i want to learn control schedule for 11kv panel? can any one send the detailed control schedule?
During FEED, you will have all the information with regards to cable. How will you calculate the MTO for MV and LV Cables? what are your considerations?
define the active power?
3 phase Motor will be given 2 phase after 2 to 5 second we given 3rd phase so Motor Run sum-time in forward or sum time run reverse direction. All time phase sequence is not change. Why motor run in reverse direction? Please Explain........
for 100 HP Induction motor service factor is 1.2(SF) we placed a VFD at the motor side load is balance with 0.3 Amp's Phase to Phase but at incoming of VFD load is un-balance with 10 to 20 Amp's what will be cause of load un balance
how much cable size required for 70 kilowatt load.
why we use the 100% and 95% stator earth fault protection for the synchronus generator ?
Parts of machine and their discription in details with suitable photo
Can we convert off line transformer to on line transformer