HOW WE WILL CALCULATE QTY. OF CEMENT,SAND & AGGREGATE
(10MM&20MM) IN Kg.
Answer Posted / achutharaj
we calculate the qty of cement,sand ,aggregate in cu.m,then
we multiple specific weight * qty of cement calculated =
qty in kgs
example 1:2:4
cement specific weight 1440kg/m3
cement qty in cu.m = 0.22
cement qty in kg = 0.22*1440=322kg
sand,aggregate specific weight 1840kg/m3,1550kg/m3
| Is This Answer Correct ? | 8 Yes | 0 No |
Post New Answer View All Answers
what is yield and tensile strength of steel, if steel has yeilding strength of 60 psi than how much its tensile strength?
How cracks in concrete can be avoided?
How about the temperature of grade 35A concrete? Does it depend on the ambient temperature?
give me the rate analysis for Bituminous Macadam and SDBC
What is specific gravity???
how many minimum admixtures are used in water froofing structures
Anyone have sample questions for bhel interview.please send me as Iam appearing for the interview on 19th sep2008. Kindly send this to my e-mail: arun_prasath_n@yahoo.co.in
how to do cementicious paint for rcc walls of cw pump house
How to come 1.54 from dry to wet concrete?
The properties of concrete HA-30 and how does it differ with M 30 (specify the important characteristics like workability,strength,mix design,slump test value)and what is the standard relating to it
How to calculate the quantity of ingredients of M20 grade concrete?
what is labour consume factor in residential projects
How many % we consider for lap for reinforcement for estimates
what is the price of a cubic meter of concrete on international market?
1) a)to prepare mortar for bricklaying how much amount of water should be added for its maximum strength and workability(to avoid cracks which results, when high quantity of water is added)?is their a formula or ratio? b) suppose we want to make 1:3 mortar,what is the best way to measure cement ,sand and water and how? c)time before which freshly prepared mortar should be used? d)proper way to mix and make mortar? e)when should curing start after laying bricks and for how long?and also how many hours per day? f)what is shear wall (please in terms of layman lol) bookish definisions are confusing.... g) and last,acc to codes what are max no. of course that should be laid in a day.