what is the actual productivity of carpentor,fitter,masson
for brickwork and masson for plaster etc
Answer Posted / n.v.ramana
1)CARPENTER=150SQFT.
2)FITTER=250KG/DAY
3)MASON=300BRICKS OR 1CUM
4)MASON-PLASTER=200SQ.FT/DAY.
| Is This Answer Correct ? | 33 Yes | 55 No |
Post New Answer View All Answers
How do you determine specific gravity of cement?
Can anyone suggest how to determine scheduling of reinforcement of floor beams from Staad model,other than clicking each beam respectively 7 noting down the values ?
how much required strength of cement concrete bricks(size 230x115x75mm)
How many times we can use Fresh bentonite ford wall execution? Would like to know the clear concept of recycling. After flushing can we use it for another time time for flushing? Or we have to use it for for excavation only?
The concrete slump recommended for beams and slabs; is?
How to do bbs in excel format
what might be the problem faced in the near future if the M-sand is used in the place of river sand during wall plastering? (As per IS)
What is unit weight of roadway layer.. 1.bitumen 2.sand 3.soil 4.concrete 5. aggregate give me some reference for this answers
What is the difference between shear and tensile strength?
how to calculate the mortar for 10'*10' size room for both plastering and for masonry work?
What in your opinion makes you the most suitably qualified candidate for this post of civil engineering technician?
Design an underground tank of internal dimensions 6m x 3m x 3m. The soil surrounding the tank always remains dry. The tank shall be provided with a roof slab. The soil weighs 16000 N/m3 having an angle of repose of 30.
Can inverted beams used in pipes during construction? If yes, explain how it can be implemented?
Why Should Curing Not Be Done By Ponding And Polythene Sheets?
What is the coeffiencent Friction Angle between Steel and Ashphalt?