How to calculate the no of bags required for 12mm thick 1:6
plastering?
Answer Posted / krishna prasad
as per CPWD Norms, cement required is 7.20 bags for 12 mm,
with 1:6 cement mortar plaster. Actual calculation gives
7.00 bags, in our calculation we have to assume 20% cement
for filling voids in the sand and 20% cement for uneven
surface of the brick/block work.
for 100 sqm, CM required willbe 100 x 0.012 = 1.20 cum
cement required will be 1.20 cum x 1/7 = 0.1714 cum
add 20% for filling voids ins and - 1.20 x 0.1714 = 0.206
cum
add 20% for unevenness in the block work/brickwork=0.206 x
1.2 = 0.2472 cum
each bag of cement weighs 0.0345 cum,
Hence, cement required for 100 sqm of plasstering will be =
0.2472/0.345 = 7.16 bags. That's it.
Is This Answer Correct ? | 29 Yes | 7 No |
Post New Answer View All Answers
reinforcement slab, beam and column formulas?
Design an underground tank of internal dimensions 6m x 3m x 3m. The soil surrounding the tank always remains dry. The tank shall be provided with a roof slab. The soil weighs 16000 N/m3 having an angle of repose of 30.
What distance in meters on the ground is the equivalent of one second of arc in longitude or latitude?
what is project?
what is the cost of rcc roof casting of 400 sq. ft. in kolkata
For sloping slabs or sloping beams why the tension steel from either side of ridge is taken into compression zone of other side?
Why are pull-out tests performed for soil nails?
LET ME KNOW HOW IS CALCULATE RUBBLE WALL .3'00" IN BOTTOM 1' 6" IN TOP HEIGHT 8' 0" AVERAGE. length 200'00". please give correct answer.
1) write Short notes about Shellow & Deep well? 2) What is the full form of SPT & SMB? write short notes. 3) write short notes about efficiency of Riveted joint.
What is the ratio of grades m5, m7.5, m10, m15, m20, m25, m30, m35, m40?
how much need cement bags for block work of wall approx 1000 hollow blocks 20x20x40cm
What difference comes in constructing of house and a housing complex like society
Why should pumping be not used in case of concreting work?
for Precast foundation howmany days required we can shift the foundation with american Standards i need reference with section any body can help
Design a rectangular channel.