what are the problems are there
if power factor is leading
Answer Posted / sk arman
When the power factor is leading, the capacitive kVAr is
more than the Inductive kVAr and this still has to be
supplied by the source. As kVA is the vector sum of kW and
kVAr, still for the given kW, you have to produce more kVA.
Alternately, for the given kVA, you can only convert
partially into useful work.
Secondary effects are voltage boost in the system,
availability of stored energy to feed the fault in case of a
fault, increase in the asymmetrical component of fault
current, increasing thus the peak value of the fault
current, etc.
| Is This Answer Correct ? | 2 Yes | 1 No |
Post New Answer View All Answers
sir i used 3 hp of motor for spraying pump, other home light and other home items which size of allminium pvc wire ix used
what is PID control in VFD drives?
Installation method of self treated earth electrode.
Dear all, I'm manikandan I have done by DIPLOMA EEE from 2011 , I have 5 years of experience from Power plant instrumentation field , which one field is give long life & which one field is best ,I confused a lot and also I'm studying AMIE, can I choose which department from Section B examination? pls tell me
how is control wiring coding is done in a CRP panel ?
I want to know how to calculate the size of electricity cable in building?
what happen when power factor of 2 parallely operated transformer become equle?
what do w do when the output of generator is fluctuating?
Will any motor burn if voltage provided is lesser than the rated voltage???? If yes, then how is speed control possible with voltage control
How can find thermal state value in relay for calculate thermal overload.
how make megger test for control cable like 12c x 1.5mm and what it apply voltage and test timing details.
What is the meaning of floating point earthing in battery backed systems ?
Why synchronous motor is used in power factor improvement,dc series in lift
i have 3500 amp load and select current transformer and perches.how i calculate .please understand
What are the specifications for conducting earth leakage test as per IEC standard?