how to calculate no. of bricks for 1 cft?
how to calculate cement and sand in cft?
Answer Posted / nadim shaikh
Multiply the size of brick and get the volume ffor e.g.
4 inch brick
= 9"x3"x4"
=0.75 x 0.25 x 0.33 =0.061875 cubic foot
Now 1÷0.061875 = 16 bricks
In any kind of BRICK WORK 33% mortar is assumed in one cubiic foot
That is in 100 cubic foot 33% Will be 33 cubic foot
Consider mortar mix ratio 1:6
Therefore for cement = 33 ÷ 7 (addition of 1 and 6)
=4.71÷1.25 (1 cement bag is 1.25 cu.ft.)
=3.768 ~3.8 bags
Sand = 4.71 × 7 = 33 cu.ft
| Is This Answer Correct ? | 63 Yes | 38 No |
Post New Answer View All Answers
1m square 20mm plastering how much of water need curing work
how much need sand and cement for 1 cft roof construction?
What is demising walls?
What is reinforced concrete?
With reference to construction of state highways, please let me know the total Bill Of Quantities as per the following details:- 1) Subgrade - 500 mm 2) Granular Sub-Base (GSB) - 200 mm 3) Wet Mix Macadam I (WMM I) - 150 mm 4) Wet Mix Macadam II (WMM II) - 100 mm 5) Dense Bituminous Macadam (DBM) - 60 mm 6) Bituminous Crust (BC) - 40 mm Road Length is 44 Kms. Road Width is 7 mtrs. Please provide the BOQ of each layer as per Compacted Factor & Loose Factor both. Also, if possible please provide me the approximate details of total material required (all categories viz. soil, gravel, stone aggregrate, sand, bitumen etc.) as per general mix design prevailing in India. Thanks & Regards -- Rokr
Find out Cutting Length of Steel for Right angle Triangle? Where Opposite Side 4m, Adjacent side 6m. (Assume cover 40mm)
How to calculate material and labor required for 100 m2 plaster?
why top layer of block work shoud be full size if any cut block adjustable than another layer?
Which are the top apps for you civil engineering?
Gave a cantilever beam with 3 legs.Told to draw the bending moment diagrams, axial force diagrams and shear force diagrams.From BMD he asked to show how the reinforcement will be provided on the tension side.
What is the wall thickness of NP-3&NP-4 hume pipe as per I.S code
how to calculate spacing rod in column
why is M25 and Fe 500 assumed to be most economical? i feel it is not.This is because higher grade of concrete and steel has higher lapping length and anchorage length compared to lower grades..
how to calculate cost of raw materials of a building for 1000 sqft & also consolidated cost of labour in a 1000 sqft building
The mixture of different ingredients of cement is burnt at?