Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...

how we can calculate the transformer size.

Answer Posted / satya mahesh

load factor(LF) and utilization factor(UF) will play a
major role in transformer selection.
Connected load-4810
Maximum demand in a month-1582 Amps
Average load which will be the average of running loads
came in a month-1173 Amps
LF=average load/max demand
=1173/1582
=0.74
UF=No.of hours running Equip/total hours in a month
=(30*20)/(30*24)
=600/720
=0.83
Transformer size= Connected load X LF X UF
=4810 X 0.74 X 0.83
=2954 Amps
for 2954 Amps 2500 KVA(3484 Amps) transformer was suitable
in continution to the future loads also.

Is This Answer Correct ?    2 Yes 1 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

Explain in details how you would react to an unexpected incident when your supervisor or manager is not around to give instructions?

8156


difference bewteen reverse current and alternating current

2291


what is the difference b/w ATS and HTS?

2238


What will be in Mahagenco Trade Test Exam? I want to know the same.

3747


Why control of DC motor is simpler?

2499


We have Diesel generator of 200KW. fuel consumption is always same,even connected light load or full load. Is it right?

2240


what is earth fault relay 64T, why it is used in main Incomer and neutral CT of Transformer.

3836


I want to put this query to SENIOR & EXPERIENCED ELECTRICAL ENGINEERS. 1)I want to know about the control circuit diagrams for control panels. I found it difficult to understand. Is there ant booklet through which we can learn the circuit diagrams? 2)I want to learn about conduiting, laying cables, preparing cable schedules and various techniques which is the part of building infrastucture(construction field). I don't have any experience in this area. I have experience in control panels only. that's why i am not getting any opening in building infrastucture (construction field).Can I get the job in this field as Trainee Engineer? How to enter this field? I need job in PUNE

1988


I AM A ELECTRICAL PANEL BOARD DESIGN ENGINEER.IF I GO ANY INTERVIEW ,TECHNICALLY WHAT ARE QUESTIONS I WILL FACE FROM INTERVIEWER?

12945


concept of busbar and load dispatching..?

2495


In hydel power plants, L.A's, S.C's are placed inside the control panel boards. what is the purpose? [already the total body was earthed to ground.]

2026


If the earth is a good conductor of electricity, why don't people get shocked every time they walking on earth?

1897


Explain and give me an example of a time when you had to explain some new procedures to your co-workers for quality service delivery, how did you go about it?

2035


ho can we calculate the conductor insulation value according to their ratings like voltage,current etc.how insulation value related with voltage,current and power of amachine

2159


sir, iam a electrical engg graduate and i want to go in automation sector and for this i have decided to do industrial training for this,plz suggest me some good institute for the same in delhi,ncr. my degree percentage is 58%, can i get job after doing training, plz help....

2091