Answer Posted / a.k.pathania
Concrete cube testing is done using compression testing
machine. Cubes of dimensions 150x150x150mm are casted and
cured properly and tested for 3,7 & 28 days strength. You
can refere codes- IS 516 for cube testing and IS 456 for
concrete-general. Also refer SP-23/24. Concrete mix design
can be done with IS10262.
| Is This Answer Correct ? | 13 Yes | 3 No |
Post New Answer View All Answers
What is the Roll of Water Bonding under VDF road?
Gave a cantilever beam with 3 legs.Told to draw the bending moment diagrams, axial force diagrams and shear force diagrams.From BMD he asked to show how the reinforcement will be provided on the tension side.
While doing civil foundation of machinery. How will you process for it? & We also fixing plates at top surface of foundation, then what is the procedure?
What was asked in isro civil interview
Forces in a Shear Wall are in plane or out of plane ?
what could be the production cost of 1 cum of concrete by CP30 plant
A 16 pile group, consisting of diameter concrete piles, were cast in situ in a clayey soil whose unconfined compressive strength is 1100 psf. Each pile is 60 ft long and the pile spacing is 2.5 times the pile diameter.The water table is at the ground surface and saturated unit weight of the clay is 118 lb/cu.ft. using a factor of safety 3 and a reduction factor =0.45, compute the allowable capacity of the piles acting as individuals
Dear Sir, I work in hydro project. I want to hire Scorpio/ Bolero on monthly basis. But how can i justified its amount (Hourly basic). Please solve my problem
Explain the different types of roofing systems?
How many bricks are there in 100cft?
I what know about life time of frp tank plz explain about it specifications & other details
can we use PPC for concrete wall, If yes, what is the concrete (PPC & OPC) grade for Non- load bearing concrete wall, load bearing concrete wall & for cellar retaining wall.
How to do rate analysis for concrete work including shuttering work?
factory shed foundation l=4, b=3' d=8' rcc foudation for top to bottom pl tell me cement ,steel ,sand ,labour cost ,excavtion,soil is weak not so hard
What is meant by a context menu in a cad software?