How to Concrete cube test method and required result in
3days & 7days & 28 days, for all grade of concrete which
refer the is code no.
Answer Posted / a.k.pathania
Concrete cube testing is done using compression testing
machine. Cubes of dimensions 150x150x150mm are casted and
cured properly and tested for 3,7 & 28 days strength. You
can refere codes- IS 516 for cube testing and IS 456 for
concrete-general. Also refer SP-23/24. Concrete mix design
can be done with IS10262.
| Is This Answer Correct ? | 13 Yes | 3 No |
Post New Answer View All Answers
What is the amount of work done by a carpenter, bar Bender and plaster Mason in interior and exterior plaster
can we find any technical issue if we are gong to change the dimensions of steel beams from one type to another type IE if there are any equievelant data base to find solution for problem of changeing sectios of beam from one type to another with the same cross sectional area.
Define Workability ?
when reinforcement binding completed if there is more cover than the required what is the solution to reduce the cover?
what is the venturi effect in buildings? what is green house concept?different types of dams? which dam is economical arch dam or gravity dam. what are the conditions favourible to both of them?
how to Concrete cubes testing curing time 7 days casting date 24.05.17 testing date ?
How to calculate(Thumb rule) the consumption of steel per cubic meter for different concrete members.
what is the formula to find the sttel (bar)length in beam having bent up at l/4 t 45 degree & 60 degree.
If density of cement is 1500 Kg/m3, the how is specific gravity 3.15 ? (Density of water is 1000 Kg/m3)
what is idealized curve for concrere and steel
how i can tak Quantity of mortar in block work
how to calculate the size of triangular ring in rcc column?
What is change order request?
Civil engineering material testing Standard results
Hi all, please guide me about the volume. And percentage. Of steel fibre to be used. My project. Is Sifcon.