How to Concrete cube test method and required result in
3days & 7days & 28 days, for all grade of concrete which
refer the is code no.
Answer Posted / a.k.pathania
Concrete cube testing is done using compression testing
machine. Cubes of dimensions 150x150x150mm are casted and
cured properly and tested for 3,7 & 28 days strength. You
can refere codes- IS 516 for cube testing and IS 456 for
concrete-general. Also refer SP-23/24. Concrete mix design
can be done with IS10262.
| Is This Answer Correct ? | 13 Yes | 3 No |
Post New Answer View All Answers
The definition of national highway
What are some structures that may be subjected to fatigue?
Why is the statue of liberty made of copper?
How many % we consider for lap for reinforcement for estimates
What is the ideal size of the living room ranges from small to large size?
1.Fe500 and Fe550 having more yield strength than Fe415.But why are we prefering Fe415.? 2. d^2/162 formula for knowing the steel wt/m apply all these three? Thanks.
Suppose you planning to paint newly fabricated workshop building made of structural steel of 10 tons total mass. How many litters paint primer for 1 coat and 2 coat of top coat?
in the earthquqke the profile of water on dam is parabolic or not
For making a new road in a village having a school & hospital , tell the steps of construction systemically ?
where tie beam is used? what is the pupose? what dimension of tie beam can provided and number and diameter of steel bars to be used between the columns of 1333mm and 1400.
How much material will consume for following specification water tank (9*7.5*6 feet)?
Time required for curing of wall tiles before fixing
WHAT DLC DESIGN IN CONSTRUCTION
how ratio is calculated for any grade of concrete. for e.g. sppose M20 requires(x;y:z) quantity of cememt sand and aggregate.
2nd and 4rt angle elevation used in which country ?