Cube tests of concrete are failed at 7 days and 28
days.What is your next action?

Answer Posted / prabhakara rao.b

Go for NDT If it is not satisfied go for Core test that
is also failed go for there possibale demolisan that coloum
it is not possible we go for Restrengthing.

Is This Answer Correct ?    4 Yes 3 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

How to calculate Cement in bags ,sand in sqft and aggregate in sqft for 1cum M25 grade concrete

1278


plz.show development and anchorage length in simple diagram.

2102


Anyone have sample questions for bhel interview.please send me as Iam appearing for the interview on 19th sep2008. Kindly send this to my e-mail: arun_prasath_n@yahoo.co.in

1604


how pumping of concrete effects the quantity of material used in it?

1297


the water is flowing through a velocity of 1.5m/s in a pipe of length 2500m and dia 500mm. at the end of pipe a valve is provided. find rise in pressure 1. if the valve is closed in 5 seconds. 2. if the valve is closed instantaneously. take value of c = 1460m/s, pipe to be rigid and bulk modulus of water - 19.692x10' n/sqcm

1890






What are the applications of cad?

677


Explain the latest method to detect a crack in a building?

684


For what building Built-on balconies are preferable? What are the advantages?

724


explain what do you mean by the property development.

1632


Define What happens to Load at yielding ?

1335


what is pile and deam foundation

1813


how to find out hard strata in bored pile when the DMC method adopted.

5334


minimum number of bars in a beam? minimum and maximum column size and beam size ? minimum and maximum aggregate size used in multistorey residential building for columns,beams,slabs?

4875


What is a kip?

724


Explain the different types of roofing systems?

777