Cube tests of concrete are failed at 7 days and 28
days.What is your next action?
Answer Posted / prabhakara rao.b
Go for NDT If it is not satisfied go for Core test that
is also failed go for there possibale demolisan that coloum
it is not possible we go for Restrengthing.
| Is This Answer Correct ? | 4 Yes | 3 No |
Post New Answer View All Answers
I need to do a Compressive Strength Test for a specimen made of Rubber. Before doing the Test on the Machine, I need to have an idea of the Minimum and Maximum Compressive Strength or Yield Strength of the specimen. How can I calculate that?
What type of tensile strength is handling by crank in beam? Thanks.
how to calculate cut length of re-bar in a circle . because we not place same length of re-bar in whole circle maximum in center and minimum at corner so how to calculate middle bars???
a rectangle grill of length 72 inch x 20 inch width.how to calculate bar spacing ,bar consist 8 mm thickness and spacing of bar is 2 inch.. calculate no of bar with formula
Calculation of Pier Cap with tapper area?
How to plan a project
What are segregation and bleeding?
if dia of inner circle is 42 m and depth is 1.5 m and width is 1 m ,then whait is the quantity of steel?
The internal dimensions of a wire house 15m*5.6m and the maximum height of piles is 2.70m. What is the maximum number of bags to be stored in two piles ?
wat would be the probable interview questions and GD topics for IOCL exam?
What is the purpose of Chipping in the heavy foundation?
what is your role of in previous company as a construction manager
very simple or less time consuming formula for reinforcement calculation by moment
what is conrete grade ,how are depent on concrete grad and size of concrete?
What is the cost difference between site mix and ready mix concrete per cubic meter