how to calculate concrete qty for footing using M25 grade
1:1:2 for 731 cft.
Answer Posted / s jaikumar
For 1m3 of 1:1:2
Cement 1.5/4=0.375/0.036=10.41
Sand 0.37
Agg 2 *0.37 =0.74
So for 731cft /35.28=20.71
Cement is used 10.41*20.71=215.59 bags
Sand is used 0.37*20.71=7.66m3
Aggregates is used 0.74*20.71=15.32m3
| Is This Answer Correct ? | 1 Yes | 4 No |
Post New Answer View All Answers
What are the causes of building collapse?
Stringer How many cm goes to landind
how meny typs of renging rod?
how to calculate labour strength for work for RCC,brickwork,blockwork,in &out plaster,flooring,dado,door frame & shutter,painting etc for constructing highrise building?
What is meant by Crystal Concrete?
what is the formula for Mass of cement grout (Dg)=???
What is the tallest man made structure in the world?
What are the RISKS during the project construction?
GIVE US DETAIL OF YOUR PRESENT EMPLOYMENT STATUS?
WET BULB TEMPERATURE AND DRY BULB TEMPERATURE?
please send me bhel questions on rupesh.017@rediffmail.com
what is the name of shuttering oil used in oman
What is the standard volume of pharma in cub ft
How to calculate volume of concrete & steel on tank foundation & ring wall ?
how do we design mix ratio?