plz give me the rate of RCC(1cuM), PCC(1 cuM), Brick Work
(1sqM)?
Answer Posted / amitkumarkushwaha
rcc for per cum
rate 4750
pcc per cum rate
25000
brick work rate per sqm 4000
| Is This Answer Correct ? | 14 Yes | 15 No |
Post New Answer View All Answers
if size is 235cmsx15cmx100cms so how many cement bags and how many sand bags are used for concrete mix
how do you calculate the quantity of steel,cement for plinth beam. (example size 41'*0.58'*1.08')
silt%= silt volume/ silt+sand volume is this right?
what is the water-cement ratio of mix design while 30mpa in 7 days?
How can we calculate 8- storied Madrasha Building pile capacity by taking SPT value at site?
Process of pcc in wateredug
How many times we can use Fresh bentonite ford wall execution? Would like to know the clear concept of recycling. After flushing can we use it for another time time for flushing? Or we have to use it for for excavation only?
2nd and 4rt angle elevation used in which country ?
what is tension footing?
What is the mix propotion of M10,M15,M20,M25,M30,M40,M50.M60 cement content,aggrigate,sand and water ratio.
in staad pro. modelling for a parallel scissors chord truss, when i assigned roller support i.e fixwd but with all Fx, FZ, Mx, My and Mz release except Fy... the analysis results " in stability at a joint, with direction Mx or My..what could be the reason...anyone please explaing
Critical Path Method is...
how to check and keep control on the wastage of material at site
What is Base Shear ?
what is the name of shuttering oil used in oman