Answer Posted / binod
THE FOLLOWING TEST ARE THE MINIMUM REQUIRED BEFORE CHARGING
A TR.
1)short cicuit test
2)opencircuit test
3)insulation test
4)magnetic core blance test
5)tan delta test
6)transformer oilo B.D.Vtest
7)silicagel color test
8)w/t&o/t functioning test
9)buchhols contact operation test
10)prv working test
| Is This Answer Correct ? | 6 Yes | 0 No |
Post New Answer View All Answers
what are the basic insulation levels & what its Unit
how r charge carriers produced
we have two motors 1250kW,6.6kV to be coupled on the same shaft ,so please provide assistance for their synchronisation.
What is rotary phase converter?
Details about Flux Compensated magnetic Amplifer starter for motors
from generating station If 400v LT line length is 1000m how much voltage is drop and how do i calculate it? which cable will be use for this line?
HOW TO REDUCE POWER PLANT AUXILIARY POWER CONSUMPTION?
Explain difference between stand by earth fault and residual earth fault protection?
along with technical test papers
Define coil span?
XYZ
How good are you in resolving the commercial issues to Employer's advantage?
How to confirm the Phase shifting Transformer VECTOR GROUP relation , as below ZNy11.45d10.45-ZNYy0.15d11.15
Draw a SLD for main panel for school having connected load of 1200kw and emergency generator 200kw.also show the increase of additional load of chiller 225kw in the lv panel indicating meter postion size of transformer ,cables and capacitor bank.
how the synchronizing is obtained at bus couplers in grid substation? (because there we cannot change the frequency in one of transmission lines like in generator synchronization)