If the load is 10Kw and power factor has to improve from 0.5
to 0.8,how can we select the capacitor rating
accordingly.Illustrate by showing formula?
Answer Posted / prasad damodar bhoir
kvar= kw (tan phi 1- tan phi 2)
cos phi 1= 0.5, phi 1= cos inverse 0.5= 60
cos phi 2= 0.8, phi 2= cos inverse 0.8= 36.86
kvar= 10 (tan60 - tan 36.86)= 10 (1.73-0.74)
kvar= 9.9
| Is This Answer Correct ? | 4 Yes | 0 No |
Post New Answer View All Answers
What does a Bode plot tell you?
What is the exact minimum vale of voltage between an earth and netural which can damage or can do malfunction of the electronic equipments ? If this is mentioned in any book, pl.give reference.
I completed my BE EEE degree 2006 .... which license should i apply .... ?????
What is relation between transmission lines & Communication lines ?
What are the functions of temperature scanner in power transformer?
what are the assumptions made in swineburne's test?
what do w do when the output of generator is fluctuating?
how can found motors folt current ? how can disided circuit breakers caoicity and breaking capicity ?
A commercial Building is designed with 14th floor levels with indoor substation of three phase transformer with rated capacity of 1000 Kva.The transformer delivered 65% of its rated capacity at 0.67 power factor lagging.Because of low power factor, the power customer was penalized and certain cost was charged accordingly based on every point percentage lower than 85%.This situation may repeatedly happen on the succeding energy bills of power customer.The power customer is desired to improve its historical power factor of 0.67 lagging and no further penalty be impose by the local power company on the next bill. Q: Identify the appropriate solution you want to offer to Client?.Justify SCIENTIFICALLY and MATHEMATICALLY the principles behind the solution.
what a function diesel generetaor turbo charger & turbo charger is more heated explain reason ?
hai now i am working as a electrical design engineer in construction field can i get a job in oil and gass field or power plant project as a electrical design engineer?
Parts of machine and their discription in details with suitable photo
WHAT IS MEANT BY INSULATION CLEARANCE IN VACCUM?
what is the string efficiency
What are PLC leader logic program method