1 Cum Brick Work CM 1: 6 - How Many Bricks ,sand,Cement
Required? Brick Size 9" 4.5" 3"
Answer Posted / shahvez
By Analysis of Rate-2007
#Bricks of class designation 7.5 in foundation and plinth
in :-
Brick with wastage = 494
Mortar = .25
Cement Ratio is 1:6, then
Cement=(.25/(1+6))*1 = .0357 cum
Cement in Bags = .0357/.034722 = 1.0286 bags
Sand = (.25/(1+6))*6 = 0.2143 cum
= 0.2143 * 35.29 = 7.56 Cft
# Bricks of class designation 7.5 in superstructure above
plinth level up to floor V level in all shapes and sizes
in:-
Brick with wastage = 494
Mortar = .22
Cement Ratio is 1:6, then
Cement=(.22/(1+6))*1 = .03143 cum
Cement in Bags = .03143/.034722 = 0.905 bags
Sand = (.22/(1+6))*6 = 0.189cum
= 0.189* 35.29 = 6.655 Cft
| Is This Answer Correct ? | 14 Yes | 13 No |
Post New Answer View All Answers
What is progress payment?
Explain the difference between shear and tensile strength.
What are the reasons for geotechnical site investigations in uganda?
how pumping of concrete effects the quantity of material used in it?
How long does it take concrete to harden?
How to do rate analysis for concrete work including shuttering work?
what should be RCC material i.e iron rod(mm)x cement x stone x sand for laying of slab L 42'x B 22'x tk 0.375ft = 1nos & column of H 17'x15"x8" 2nos.
what is differences between ferrock and concrete ?
what is the composition of good brick ?
Why should pumping be not used in case of concreting works?
Explain major difference between auto level and dumpy level?
Where can I get a Text Book on Design of Blast Resistant Buildings in PDF form.
Why was the empire state building made of steel?
residential projects,structural.
what is the breaking strength of wall tiles