how to caculate cutting lenght in bar bending schedule for
180 degree bend

Answer Posted / anvesh

the standard bending shape is U..
the minimum cuttin length for 90degres bend should be 4d. nd
it should not 3d
for better grip..
the total length reuired for hook is 12d measured starting
from the point the bar start to bend.

Is This Answer Correct ?    3 Yes 2 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

Which tests are performed on soil to decide the type of foundation to be provided.

1644


What is the compressive strength of fly ash bricks?

698


Can any body help me out by telling hoe swelling pressure test of soil is carried out ? some body told me the procedure & formula (change in length /116.3*100%) but still i am confused ? pls help.

1415


Define mirror?

805


what post do you prefer to work in this company and why do you think you can serve better in such position?

2250






Minimum concrete cover in slabs, columns, beams, foundation and other st?

679


Mention different types of roof systems?

733


What are the applications of the modulus of elasticity?

665


Can compresive strength test for concrete at 1 day age possible to carry out? If yes, which IS code describes the procedure for such testing?

1591


What is the use of water table & Kreb stone for drain

1371


I need model question papers for writing the Dubai municipality exam,for G+1

9409


hi, i am appearing in HPCL(CIVIL ENGG.)exam. plz send me placement paper of this exam if u are having

2043


What happens when,in Prestressed girder the HDPE duct and cone size is provided more than required? (technical answer expected)

1676


What is the standard rate of installing ties for column(60cmx60cm) and beams(50x850)(weight)

1198


how to convert sand in Cft to Kgs

1484