how to caculate cutting lenght in bar bending schedule for
180 degree bend
Answer Posted / anvesh
the standard bending shape is U..
the minimum cuttin length for 90degres bend should be 4d. nd
it should not 3d
for better grip..
the total length reuired for hook is 12d measured starting
from the point the bar start to bend.
Is This Answer Correct ? | 3 Yes | 2 No |
Post New Answer View All Answers
Which tests are performed on soil to decide the type of foundation to be provided.
What is the compressive strength of fly ash bricks?
Can any body help me out by telling hoe swelling pressure test of soil is carried out ? some body told me the procedure & formula (change in length /116.3*100%) but still i am confused ? pls help.
Define mirror?
what post do you prefer to work in this company and why do you think you can serve better in such position?
Minimum concrete cover in slabs, columns, beams, foundation and other st?
Mention different types of roof systems?
What are the applications of the modulus of elasticity?
Can compresive strength test for concrete at 1 day age possible to carry out? If yes, which IS code describes the procedure for such testing?
What is the use of water table & Kreb stone for drain
I need model question papers for writing the Dubai municipality exam,for G+1
hi, i am appearing in HPCL(CIVIL ENGG.)exam. plz send me placement paper of this exam if u are having
What happens when,in Prestressed girder the HDPE duct and cone size is provided more than required? (technical answer expected)
What is the standard rate of installing ties for column(60cmx60cm) and beams(50x850)(weight)
how to convert sand in Cft to Kgs