what is right time of slab DE shattering and beam boo tam.
Answer Posted / ananth
span length below 4.5m 7 days
span length over 4.5m 14days
| Is This Answer Correct ? | 1 Yes | 0 No |
Post New Answer View All Answers
Exterior Joints,define
How to testing voids of filled aggregate in bitumen mix design
Explain the different types of roofing systems?
in staad pro. modelling for a parallel scissors chord truss, when i assigned roller support i.e fixwd but with all Fx, FZ, Mx, My and Mz release except Fy... the analysis results " in stability at a joint, with direction Mx or My..what could be the reason...anyone please explaing
how to prepare site mix design
If specific gravity of cement is less than 3.15 what is the cause?
How is calculate the cube molt
What is the difference between yeild strength and compressive strength of steel???
What is the l/d ratio of cantilever beam?
WHERE CAN I GET THE PREVIOUS QUESTION PAPERS OF APGENCO FOR THE THE POST OF Tr.ASSISTANT ENGINEER(CIVIL)
What is absolute pressure? How absolute pressure is calculated?
how many shuttering material required for 1000 sq.m built up area.
How to calculate or what is the process of calculation for making 1Metre squre area by AAC Blok which quantity of Cement, Sand & Chips are to be required?
I have completed building maintenance course in mcvc stream .. can I apply for the post of " sthapstya abhiyantriki sahayyak"?
What is the difference between Rock And Murrum. How to claim that excavated material is not a murrum but rock.