How we calculate the cement for the M 15 normal concrete with
aggregate size is 40 mm ?
Answer Posted / raju
for M15 proportion is 1:3:6
assume wet volume 1 m3 of work
to produce 1 m3 of wet volume we need 1.54 dry volume
cement qty=1.54/1+2+4=0.22 m3
hence no of bag=0.22*1440/50=6.33 nos
sand qty=0.154*2=0.308 m3
agg qty=0.154*4= 0.616 m3
| Is This Answer Correct ? | 1 Yes | 7 No |
Post New Answer View All Answers
For 1 bag cement how i will calculate sand and metal aggregate;Here the mix proportion is 1:2.49:2.38
quantity of sand and cement for 10m2 plastering 10mm thick for the ratio of 1:4,1:3and its leabour data
What are the methods of measurement? Describe it shortly
What is the bowing depth after stressing of PSC Girder of various spans and various dia of strands?
Wats the formula of eccentric footing and how was calculated from concrete qty
List out some of the software program that can be useful for architect?
I have to design brick column and footing (note: without any reinforcement). Can somebody post me the design or suggest a book where i could possibly find the design? Plz help very urgent
What are the Types Of DPC and its Thickness used?
how do you calculate the length of "L" of main & distribution bar for reinforcing of raft footing
What are the different approaches in designing the floors of the service reservoirs?
how to tie 10 legged stirrups
What is difference between combin footing & rapt footing
What is meant by cad?
how many cement used in single story residential building per sqft
how to find out hard strata in bored pile when the DMC method adopted.