How we calculate the cement for the M 15 normal concrete with
aggregate size is 40 mm ?
Answer Posted / mangesh
for M15 proportion is 1:2:4
assume wet volume 1 m3 of work
to produce 1 m3 of wet volume we need 1.54 dry volume
cement qty=1.54/1+2+4=0.22 m3
hence no of bag=0.22*1440/50=6.33 nos
sand qty=0.154*2=0.308 m3
agg qty=0.154*4= 0.616 m3
40 mm is max size of agg & it is the std value
Is This Answer Correct ? | 5 Yes | 6 No |
Post New Answer View All Answers
What is the life of anaerobic Digester if it is used for municipal solid waste digetion.
why should we use 20mm graded metal only in vrcc?why we shouldnot use 40mm metal?
pile load testing procedure
States some of the commonly used commands in cad software’s?
Maximum cement content in 1cum for RCC and PSC? (please give IS,IRC referance?
for 200 kg of cement how is the mix proportion in kg for m25 grade of concrete
What is hybrid foundation?
1) What is meant by C-soil in geotechnical Engineering? 2) What is Eve board? 3) What will happen when heat is applied to cement? 4) what do you understand by the lateral dimention ?
What is the per cu. mt. price of ready mix in Gujarat region.?
use ofr concrete as per grade ?
How to take labor charges for construction of 1cum of concrete?
what is the anchorage length of reinforcement.
how to frame the sentence in voucher pad ? Description : 1.Food Expenses during site visit 2.Stamp Paper approval expenses 3.Travelling expenses 4. sweet distribution
What should be the maximum allowable time for placing ready mix concrete? The specification requires concrete placement within 90 minutes of batching at the plant. What is the significance of this 90 minutes & should this be used as a rejection criterion? What effects does the concrete has after that time period?
how to calculate freeboard in under ground water tank and technical details