How we calculate the cement for the M 15 normal concrete with
aggregate size is 40 mm ?
Answer Posted / mangesh
for M15 proportion is 1:2:4
assume wet volume 1 m3 of work
to produce 1 m3 of wet volume we need 1.54 dry volume
cement qty=1.54/1+2+4=0.22 m3
hence no of bag=0.22*1440/50=6.33 nos
sand qty=0.154*2=0.308 m3
agg qty=0.154*4= 0.616 m3
40 mm is max size of agg & it is the std value
| Is This Answer Correct ? | 5 Yes | 6 No |
Post New Answer View All Answers
hi, i am appearing in HPCL(CIVIL ENGG.)exam. plz send me placement paper of this exam if u are having
Permissible wastage of cement as per IS code ? In which IS code I get it?
As per Kandal suggestions, we have implemented rolling starts on 140 (+/- 5) degrees and we kept 3 rollars to complete the rolling before falling 125 degrees and the Aggregate AIV is below 22. But When the DBM bed is being rolled 3rd high viabration, (Before 1 plain & low ,2 high Viabrations), the aggregate is getting sharp edge agg. projections are damaged. As the literature is said that, the VG-30 Grade having better control the temp. susceptibility than Penetration grade. if so we could not get this problem at site. But we are facing on site. let me know.
What is the coeffiencent Friction Angle between Steel and Ashphalt?
What is an ice dam sock?
Forces in a Shear Wall are in plane or out of plane ?
What is a tensile strength? What is the tensile strength of wood?
what is conventional shuttering rate per square feet of built up area? what is Mivan shuttering rate per square feet of built up area? what is coupler shuttering rate per square feet of built up area?
Which condition will prevail for the design of a swimming pool ? When the pool is empty or when it is filled ?
estimate quanitity of bricks(19x9x9cm without mortar), cement & sand in 10feet X 10feet wall ?
how we calculate the grade of the Bituminous materials.?????
Gave a cantilever beam with 3 legs.Told to draw the bending moment diagrams, axial force diagrams and shear force diagrams.From BMD he asked to show how the reinforcement will be provided on the tension side.
what are the duties of Site Engineer in work site?
How to Know that veriation acceptable in CPWD Work Of 1:6 Cement Mortor Received Lab test report.