How we calculate the cement for the M 15 normal concrete with
aggregate size is 40 mm ?
Answer Posted / mangesh
for M15 proportion is 1:2:4
assume wet volume 1 m3 of work
to produce 1 m3 of wet volume we need 1.54 dry volume
cement qty=1.54/1+2+4=0.22 m3
hence no of bag=0.22*1440/50=6.33 nos
sand qty=0.154*2=0.308 m3
agg qty=0.154*4= 0.616 m3
40 mm is max size of agg & it is the std value
Is This Answer Correct ? | 5 Yes | 6 No |
Post New Answer View All Answers
How to calculate carrying capacity of the existing water supply trunkmain
How to calculate the cement plastering for circular and rectangular water storage tanks and how to calculate the area of circular and rectangular floor?? Please help me
What out turn civil works
why does the most of civil engg is not intersted to going for teaching field?
how to Concrete cubes testing curing time 7 days casting date 24.05.17 testing date ?
what will be density of a cement bag if its weight and volume are 50kg and 1.25 cft respectively???????
for G+2 residential building how much quantity of required in foundations,sub & superstructures per sq ft area
Dear sir, i want to NBCC & NTPC previous exam papers email Id : madhu_bingi@yahoo.co.in
While calculating the weight of the steel per running meter, the formula used is [(dxd)/162]. Why 162 is used in denominator & how it is derived?
Describe the sections included in a typical bill of quantities
I am practising engineer. I am searching for tutorial of RCC T Girder design Example in staad pro.Do anybody has this?please help
What is meant by solid geometry?
how to calculate the mortar for 10'*10' size room for both plastering and for masonry work?
reinforcement slab, beam and column formulas?
what is Brick crushing strength(PSI)?