How we calculate the cement for the M 15 normal concrete with
aggregate size is 40 mm ?
Answer Posted / n3
for M15 proportion is 1:3:6
assume wet volume 1 m3 of work
to produce 1 m3 of wet volume we need 1.54 dry volume
cement qty=1.54/1+3+6=0.154 m3
hence no of bag=0.154*1440/50=4.44 nos
sand qty=0.154*3=0.462 m3
agg qty=0.154*6=0.924 m3
40 mm is max size of agg & it is the std value
| Is This Answer Correct ? | 4 Yes | 10 No |
Post New Answer View All Answers
What are the advantages of cad software’s?
If we are providing concrete joint in every 10m with water stopper in water tank wall then is it necessary to cut the steel at joint section?
what is escalation?how it is done?
a solid steel rod length 2m dia and 20mm vertically hangs from celling and has a collar firmly atteched to it. above the collar an annular rubber washer of 40mm th. having stifness k = 5n/mm is placed. determine maximum stress in the rod caused by mass of 5 kg falling through a height of 1.2m.
Define What is the distance between railway tracks?
how much required strength of cement concrete bricks(size 230x115x75mm)
What are the advantages of building a dam on the river nile?
What are the common ways of demolition?
What are the methods of measurement? Describe it shortly
how to clculate the %of concrete strenght achive after curing?load
Define What is a projection line?
usually hand broken stones are used for cement concrete 1:4:8 in foundation of single /two story houses with a view of economy in construction.what advantages it will give if you use machine crushed stone in place?
Is there the dry coefficient of cement is constant?
What is the use of array command?
A Cat excavator loader of 3Lm*3 heaped capacity bucket is to be used to load blasted rock directly into a crusher of capacity (consumption) of 100L