How we calculate the cement for the M 15 normal concrete with
aggregate size is 40 mm ?
Answer Posted / n3
for M15 proportion is 1:3:6
assume wet volume 1 m3 of work
to produce 1 m3 of wet volume we need 1.54 dry volume
cement qty=1.54/1+3+6=0.154 m3
hence no of bag=0.154*1440/50=4.44 nos
sand qty=0.154*3=0.462 m3
agg qty=0.154*6=0.924 m3
40 mm is max size of agg & it is the std value
| Is This Answer Correct ? | 4 Yes | 10 No |
Post New Answer View All Answers
Need help in designing a degasser tower for 2m3/hr DM plant, also send me the formulae used
explain the rale of the government in the construction industry
i am laying a base of dimensions 6.5feet by 7feet by 1.25 feet depth how many bags of 25kg cement and how many bags of 25kg sand will i need
What is the formula for figuring out how many gallons of water are in a pipe by the foot?
what is the hanekom repairing material after concreting work
Explain the term 'Gross unit rate' and identify the items that may be included in the gross unit rate.
what is work of planning deptt. in any construction compny (in road project)
How many feet are in 4 square yards?
what is spacing of wallar support of 3m column. the thickness of column is 0.25 m.
what is Bearing Capacity,How to determine it?
How to calculate the quantity of ingredients of M20 grade concrete?
how to calculate the rebar depth if forgot the foundation reinforcement (main steel)? is that any calculation or formula we have data sheet of supplier what depth what is the pull out capacity is mensioned in data sheet. if any IS code than its help full to me.
Which condition will prevail for the design of a swimming pool ? When the pool is empty or when it is filled ?
How to do base isolation for RC framed structure using ETABS software?
What is the release of lien?