Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...

how much bags of cement will be in 1 cmt of having the ratio
1:3:6

Answer Posted / kamal deep kumar

let's have calculation
for 1 cum= 1/1+3+6=.1cum it is total volume of conc't.
then cement is=.1x1440=144kg
so bag is 144/50=2.88 bags.

it is also perfectly thumb rule.

Is This Answer Correct ?    5 Yes 5 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

what is the breaking strength of wall tiles

2525


WET BULB TEMPERATURE AND DRY BULB TEMPERATURE?

2374


What is the compressive strength of fly ash bricks?

1140


What is proportion of PCC Grade G?

2054


what is detail procedure of eccentric footing? plz. give solved exmple?

2317


can you mail me detailed procedure,entire syllabus and practice papers of mpsc civil engineering branch.I am in third year now

2171


As we know that steel is a tension member but why we are using STRUCTURE STEEL as a COLUMN (Without concrete) where column is a compression member and compression strength of steel is very low

1674


howto calculate the quantities of material used in fly ash brick after finding the volume??

1696


suppose we have a tendency to make a hole on the surface of the simple supported beam, than where we goes to make it?

2060


How to testing voids of filled aggregate in bitumen mix design

1928


Why Is Propping Required For Long Structures Once The Form Work Is Removed?

1278


Why should you show Client/Engineer activities clearly on the project plan?

2419


factory shed foundation l=4, b=3' d=8' rcc foudation for top to bottom pl tell me cement ,steel ,sand ,labour cost ,excavtion,soil is weak not so hard

2104


What is the cost of formwork for columns/beams/rcc walls also what is the cost of shuttering for roof slab at height of 25 feet

2542


the water is flowing through a velocity of 1.5m/s in a pipe of length 2500m and dia 500mm. at the end of pipe a valve is provided. find rise in pressure 1. if the valve is closed in 5 seconds. 2. if the valve is closed instantaneously. take value of c = 1460m/s, pipe to be rigid and bulk modulus of water - 19.692x10' n/sqcm

2359