If we have 15000kw connected load in a factory than how much
power demand sanction should be taken from electricity board.
Pls provide complete calculation.
Answer Posted / k.prakashchandra
Only the connected is mentioned and not the peak load.
Maximum demand is registered only if that apparent load
lingers for more than 15 to 30 minutes (as set).You have to
consider load factor(?) also .Apply for 12000 KVA MD
initially and you can apply for higher ,later.Once you get
the MD sanctioned, you can not get it reduced during the
agreement period.
| Is This Answer Correct ? | 1 Yes | 0 No |
Post New Answer View All Answers
why industry prefer ht motor instead of lt motor.
what kinds of Transformer oil grade is better for power transformer ?
what happen when increase or decrease size of lamp,light.glass.
What do you mean by turns ratio of instrument transformer?
I am doing apprenticeship training at HT switch yard in NLC. How can i get electrical c license. ??? What r the rules for getting it as an apprentice? ??
draw the block diagram of fire alarm?
how can check the resistance of battery contact?
(1)The demand for electricity , the amount of renewable generation available, the amount of fossil fuel generation available and the cost of the fossil fuel generation are shown in table below period(hrs) demand(MW) renewable (MW) fossil- fuel(MW) cost of fossil fuel(MW) 00.00 - 01.00 2000 1800 2000 30 01.00 - 02.00 2300 2500 2000 30 02.00 - 03.00 2500 2700 2100 45 03.00 - 04.00 2900 3100 2100 50 04.00 - 05.00 2700 2600 2500 45 05.00 - 06.00 2400 2000 2700 50 06.00 - 07.00 2200 1800 2000 36 07.00 - 08.00 2100 1600 2000 36 Assuming that the renewable generation incurs zero cost, determine an optimal generation schedule(specifying the amount of renewable generation and fossil fuel generation used in each period, the cost for each period and the overall cost for 8 hours.)
If i have two 3000 kW motors and the whole facility requires a 10 MVA transformer. What would be better installing two 5 MVA transformers(one for 1 motor ) or just a single 10 MVA transformer for both of them. Give reasons for your answer.
Keywords: Die, Card, Coin, B/N 2 To 12
can u give me a brief idea about power line carrier communication ??
HELLO EVERYONE, I RECENTLY HAVE FOUND ONE PROBLEM, I WAS TAKING NO LOAD TRIAL OF AN HT MOTOR 920 MOTOR , 1440 RPM , 6.6 KV, WITH AUTO TRANSFORMER. AT 450 V, LOAD WAS 40 AMP AND SPEED WAS 250 RPM. BUT AS WE INCREASE VOLTAGE FROM 450 TO 480V, LOAD BECOME 41 AND SPEED REDUCED TO SOME RPM . SO WHICH PHENOMENON ACTED HERE FOR REDUCING SPEED.?? AND IS IT HAPPENING ALWAYS OR IT IS RARE? I ALSO HAVE FACED SUCH PROBLEM WITH FEW LT MOTOR ALSO.
Explain Active power,reactive power,how its related to each other , & inductive ,capacitive.
Greeting to all members, How to calculate spill current when we have different ratio CT and Class for REF(Low Imp) I have 500/1A 5P20 @line side n 400/1A CL.X @ Neutral.
Why we are use dol starter up to 10 hp