If we have 15000kw connected load in a factory than how much
power demand sanction should be taken from electricity board.
Pls provide complete calculation.
Answer Posted / ashish negi
the above calculation is correct but if we have to give our
demanded load to electricity dept. than the load should be
greater than the load as on starting motors , motors take 2-
3 times the full load cureent and at that time your MDI
(maximum demand index)will go beyond the calculated load.
so in that case your have to pay the penalty. so your
demanded load should be between 2500-3000 KVA.
| Is This Answer Correct ? | 5 Yes | 0 No |
Post New Answer View All Answers
1. What is the exact formula for one weber? for example,(one ampere = one coulomb electron of electrons crossing a point of conductor at one second. i.e, 1A=1Q/1sec)
Does magnetomonopoles exists? one maxwell equation strongly suggests no, but how about their existance in plasma?
explain remenance . differentiate high remenance type ct & low remenance type ct
distribution is maximum done by a)radial b)network c) parallel d)b & c
Can 33kva/415v transformer be run underground? If the answer is yes why and if the answer is no why?
Is it possible to make a 5P10/ CT Ratio 50/1A Burden 5VA
whit is 33kv power 300*300 cable full current with formula
is it possible to test of bus bar in high rise building without completed full floor ?
what is cathodic protaction?
Why do we avoid electrical conduits in floors at apartments?
Why is the frequency not changed during transformation of electrical energy in a transformer?
How to calculate VCB rating for 33KV ,25 MW Power line?
What is making & breaking current ???
Either the Armoured Earthing strip of HT 3 core cable have to pass through CB CT or not , why ???
When we connect the large capacitor bank in series ?