how to caculate cutting lenght in bar bending schedule for
180 degree bend
Answer Posted / vinod kumar, sriharikota
GENERALLY 90DEGREES BEND IS 2D, 180DEGREES MEANS IT IS STRAIGHT BAR THE CUTTING LENGTH IS TAKEN INTO ORIGINAL LENGTH OF BAR.
| Is This Answer Correct ? | 5 Yes | 3 No |
Post New Answer View All Answers
what is the calculation of raw material for 0.35cum of m-15
afe or not
show answer/calculate mix 1:2:4 ratio -cement-sand -metal-water
the volume of cement req for 70cum of brickwork in 1:6 cement mortar is approx is equal to 3cum 5cum 7cum 1ocum
How to calculate the cement consumption in RR Masonry in CM 1:8 for the foundation of Ground Level Reservoir
If 40 backlogs are cleared m finally with 65 percent marks . Am I eligible to get visa to US
How many litres of water used for curing of 1000sqft of slav
could u tell me how to used deform stell bar in reinforce concret?i wanna know the general using in the site!
What is the standard volume of pharma in cub ft
how to calculate 1:5:8 ratio concrete cement, sand, metal and water please give me brief calculation
If we have the center line of the Finnish road level and we want to know what level of pay would have offset the Lhs and Rhus RHS 1,2.5,5 1,2.5,5 m.
(Project Management Topic) What are the important criteria in the successful realization of the project?
How much cement,sand,bricks and water needed for 1square metre brick work?
what is polity
please what is the number of bars required for a column of 6mx6m and 450mmx300mm,its a commercial building (Church)